METRO PHASE-3 HITS HIGHWAY HURDLE

Metro’s longest line was to be launched by December, but issues in land acquisitio­n in Trilokpuri and expansion of NH-24 delayed the project

-

PROBLEM 1

Elevated alignment of corridor crosses NH-24 at two locations in east Delhi: Between Vinod Nagar & Vinod Nagar East Between IP Extension & the Vinod Nagar Metro depot DMRC erected pillars on either side of NH-24 at the two spots NHAI raised objections on alignment 4 pillars being dismantled and relocated

PROBLEM 2

Delay of land acquisitio­n in Trilok Puri

RESULT

Mayur Vihar-IP section affected, rest of line is completed. Connection to depot not complete. Delay of line by eight months. Dismantlin­g and rebuilding cost DMRC `8 crore. Why this 58.596-km Mukundpur-Shiv Vihar corridor will connect all existing depot is six lines of Delhi Metro. 39.479 km is elevated, 19.117 km undergroun­d. important There are 38 stations, of which 10 are interchang­e ones.

 ??  ??