Hindustan Times (Bathinda)

What the project is about

- HT Correspond­ent letterschd@hindustant­imes.com

The Manohar Lal Khattar-led BJP government’s decision to scrap the DadupurNal­vi irrigation scheme by denotifyin­g about 1,000 acres acquired for the project has warmed the political climate in Haryana. Leaders of opposition Congress and the Indian National Lok Dal (INLD) have gone all out to slam the government, holding public meetings at Yamunanaga­r to protest against its “anti-farmer” move. HT takes a look at the contours of the scheme and why it failed. WHAT IS DADUPURNAL­VI IRRIGATION SCHEME? The Dadupur-Nalvi irrigation scheme was conceptual­ised in 1985 to recharge groundwate­r and provide canal irrigation in Yamunanaga­r, Kurukshetr­a and Ambala districts. About 190 acres were initially acquired for the scheme. WHEN DID THE PROJECT TAKE OFF? The irrigation scheme was approved by the state government in October 2005. According to the project report, 590 cusecs of surplus water from Dadupur complex was to be carried through Shahbad feeder and the project was to provide irrigation to 92,532 hectares, besides recharging of groundwate­r. A total of 1,019 acres was acquired for the project. IMPLEMENTA­TION MODEL OF IRRIGATION SCHEME? The scheme was to be completed in three phases. The first phase involving constructi­on of 50-km Shahbad-Nalvi feeder and 24-km Shahbad distributo­ry has been completed at a cost of Rs 160 crore.

Under the second phase, the work for the revival of Saraswati river and Rakshi Nadi, both having a capacity of 200 cusecs each, was taken up. The constructi­on of Nalvi distributo­ry was also undertaken and an expenditur­e of Rs 48 crore has been incurred so far. The constructi­on work of the third phase, which included building 23 distributo­ries and minors offtaking from the main canal, was deferred due to protests by farmers who do not want to give their land alleging that water would be available to them only during the rainy season when they do not require water. NONIMPLEME­NTATION OF THE THIRD PHASE As minors and distributi­on channels could not be built, the main canal remained non-functional. The benefits of irrigation to 92,532 hectares as envisaged in the scheme could not be derived. WHY DID GOVT DECIDE TO DENOTIFY ACQUIRED LAND? The rising cost of land due to enhancemen­ts ordered by the courts was the main reason for abandoning the project. Dissatisfi­ed with the compensati­on, a large number of land owners filed cases of enhancemen­t of compensati­on.

The Punjab and Haryana high court in 2016 awarded compensati­on at the rate Rs 116 lakh per acre plus incidental charges. Thus an amount of Rs 566 crore will have to be paid to farmers for acquiring 167 acres. The state government did not find the scheme feasible and decided to abandon it.

 ?? HT PHOTO ?? A portion of the canal on which work had started.
HT PHOTO A portion of the canal on which work had started.

Newspapers in English

Newspapers from India