Hindustan Times (Chandigarh)

Capt clears air, says no rethink on closure of Bathinda thermal plant

CM says no employee will lose his job, shutdown decision taken due to lack of power demand in state and availabili­ty of cheaper power from alternativ­e sources

- HT Correspond­ent

CHANDIGARH: Chief minister Captain Amarinder Singh on Sunday ruled out reversal of the government’s decision to close down the Guru Nanak Dev Thermal Plant (GNDTP), Bathinda, pointing to the non-feasibilit­y of continuing operations.

In a statement, Amarinder explained the circumstan­ces that led to the closure of the Bathinda plant and two units of the Rupnagar thermal plant, saying the decision had to be taken mainly due to lack of power demand in the state and availabili­ty of cheaper power from other alternativ­e sources.

He said the work order had already been placed on consultant — Steag Energy India Pvt Ltd, Noida — for conducting a detailed feasibilit­y report for three units of 800MW at Guru Gobind Singh Super Thermal Power Plant (GGSSTP), Rupnagar.

After coming to power, the Amarinder government decided to dismantle the Bathinda plant and two units of the Rupnagar thermal plant terming them unviable. The government also decided to build a new plant with super critical plant technology at Rupnagar. Before the assembly polls, finance minister and Bathinda MLA Manpreet Badal promised that the plant would not be shut.

Staring at retrenchme­nt, employees, particular­ly the contractua­l staff, have been protesting against the government’s decision of shutting down the thermal plants.

Reiteratin­g that no employee would lose his job because of the closure and all workers would be accommodat­ed within the region, Amarinder said after closing down plant operations completely, the surplus manpower of the Bathinda plant shall be utilised on other works where there is shortage of staff.

“This will increase productivi­ty as it will stop increase of power generation cost over the year, resulting in savings for Punjab State Power Corporatio­n Limited, since power from the Bathinda plant was generated at a very high cost as compared with the overall cost of electricit­y in the PSPCL,” said Amarinder.

He said that no retrenchme­nt of the staff – regular or contractua­l — shall be done and all of them shall be adjusted suitably in the nearby locations, with full pay protection.

Giving details of the power situation in the state, the CM said power demand in Punjab varies widely during paddy and nonpaddy seasons.

In 2016, the maximum demand was recorded at 11,600MW in summer months and 5,600MW in winters. In winters, there is a lot of variation in the day and night time demand, with the latter coming down to around 3,000MW, he added.

Though the state has become power surplus, generation capacity is utilised fully only during the paddy season of four months, and for the remaining eight months, the power remains underutili­sed.

The CM said the thermal plant is of old design and requires more manpower for operation as compared to new power plants, which are fully computeris­ed.

At present, new plants are being installed with higher capacity units such as 660MW and 800 MW, he said, adding the old plants also require more maintenanc­e and the performanc­e of equipment comes down with the passage of time.

With change in technology, a lot of developmen­ts are taking place in the area of wind and solar energy, the CM said, underlinin­g the importance of shifting to alternativ­e sources of energy in the interest of the state.

 ?? HT FILE ?? After coming to power, the Amarinder government decided to dismantle the Bathinda plant and two units of the Rupnagar thermal plant.
HT FILE After coming to power, the Amarinder government decided to dismantle the Bathinda plant and two units of the Rupnagar thermal plant.
 ??  ??