Hindustan Times (Chandigarh)

Amritsar smart city misses solar panels installati­on deadline

- Mandeep Kaur Narula

AMRITSAR : The Amritsar Smart City Limited (ASCL) has missed the first deadline of installing solar panel project as only 35% of solar panels could be installed atop government buildings since its inception in March.

The ₹10.40-crore rooftop solar panel project was scheduled to be completed by October 30. The ASCL officials, however, now expect to complete the project by December this year.

Under the smart city project, three cities in the state – Ludhiana, Jalandhar and Amritsar – were selected. ASCL, which started its working in 2017, has a total budget of ₹1,000 crore to execute its 54 developmen­t projects in the holy city. In the first phase of solar panel project, ASCL had identified 17 government buildings in the city to install the solar panels with approximat­ely 1.5 MW of cumulative capacity.

Out of the total identified buildings, installati­on at only six

DEADLINE WAS SET FOR OCTOBER 30; OF 17 IDENTIFIED BUILDINGS, SOLAR PANELS COULD BE INSTALLED ON ONLY 6

of these buildings has been completed by ASCL in eight months. The ASCL, which has taken two years for planning and surveying the projects, is still awaiting ‘no objection certificat­e’ (NOC) for some buildings.

When asked about the delay, ASCL chief executive officer (CEO) Komal Mittal said, “The installati­on work of solar panels at 6 buildings has been completed. The project was delayed because we are still awaiting NOCS for Old DC building, police line buildings (as both are under constructi­on) and Guru Nanak Dev Hospital (GNDH).THE work on rest of the buildings is underway and the project is expected to be completed by end of December.”

 ?? SAMEER SEHGAL/HT PHOTO ?? Solar panels installed on Amritsar Improvemen­t Trust building in Amritsar.
SAMEER SEHGAL/HT PHOTO Solar panels installed on Amritsar Improvemen­t Trust building in Amritsar.

Newspapers in English

Newspapers from India