Hindustan Times (Chandigarh)

NHAI to conduct concrete test to find reason for Gurugram flyover collapse

- Abhishek Behl

GURUGRAM: The National Highways Authority of India (NHAI) will test the concrete used to construct the elevated section of Sohna Road — a portion of which collapsed on Saturday night. The agency may also review its design, as suggested by experts who inspected the site.

Three girders of the 5km elevated road fell on Saturday at around 9.50pm near Vipul Greens condominiu­m, injuring two labourers.

Light traffic and the weekend restrictio­ns in place to prevent the spread of Covid-19 helped in preventing casualties, said officials.senior NHAI officials and consultant­s to the projected had visited the site on Saturday night along with technical experts.

The damaged 40-metre section, NHAI officials said, will be removed within 15 days and fresh girders will be installed.

“A team of experts has inspected the site and it will look into the issues which led to crashing of the span. All steps would be taken to ensure such incidents don’t happen,” said RK Pandey, member, NHAI, (Project), who along with a large team inspected the site.

The NHAI also directed the contractor to barricade the accident area effectivel­y to ensure no further threat to motorists and workers, and to ensure any further failings of the structure do not result in loss of life.

“It has also been decided to increase the frequency of quality control tests, especially after concreting, and test the quality of segments and wings,” said a senior NHAI official who spoke on condition anonymity.

Manoj Kumar, member, project, NHAI, who also inspected the site said that all aspects of the collapse would be investigat­ed but it would be difficult to ascribe any reason for the incident without testing.

This is a rare incident as we follow all norms and quality control measures. We will probe the incident and take corrective measures. JP GUPTA, senior official , Oriental Engineerin­g

As per the details shared by an official of the contractor, the collapse of the span happened on pier 10 but another end of span was still hanging.

The launching and gluing of this segment happened on August 5 and stressing work was completed on August 7.

The launcher, which is used to place these spans was shifted from pier 11 to 12 on August 22 evening — the day the span collapsed.

“This is a rare incident as we follow all norms and quality control measures. We will probe the incident and take corrective measures,” said JP Gupta, senior official of Oriental Engineerin­g, the contractor.

 ?? HT PHOTO ?? Three girders of the 5km elevated road fell on Saturday at 9.50pm near a condominiu­m in Sohna, injuring two labourers.
HT PHOTO Three girders of the 5km elevated road fell on Saturday at 9.50pm near a condominiu­m in Sohna, injuring two labourers.

Newspapers in English

Newspapers from India