FINDINGS IN THE REPORT
The plant is processing around 30 tonne per day waste – only 10 % of the design capacity
The plant is designed only for processing source-segregated dry waste
Housekeeping and regular cleaning, as well as painting, is not up to the mark
Storm water management is poor
No record of air emissions, compost quality and calorific value of refuse-derived fuel (RDF)