Gzb expedites land compensati­on disbursal to farmers for eastern expressway project

- HT Correspond­ent htreporter­s@hindustant­imes.com

After regular monitoring by the Supreme Court, the Ghaziabad district administra­tion has expedited disbursal of land compensati­on and the pending arbitratio­n cases of farmers whose lands were acquired under the eastern peripheral expressway (EPE) project that envisages signalfree connectivi­ty between Ghaziabad, Faridabad, Gautam Budh Nagar (Greater Noida) and Palwal.

District magistrate (DM) Ministi S, said on Wednesday that a total of ₹26 crore was handed over to farmers as the major amount of over ₹400 crore was pending for three major projects, including EPE, dedicated freight corridor and Delhi-Meerut Expressway project.

“The amount could not be disbursed due to a number of bottleneck­s like pending cases, demands by farmers etc. We formed a committee of officials who discussed the pending issues with farmers and organised camps where nearly ₹ 26 crores was distribute­d in two days. We are expecting that the pending amount will be disbursed within a month now as we will also be working on holidays,” the DM, said.

According to official estimates, amounts of nearly ₹84 crores for EPE, ₹214 crores for dedicated freight corridor and another ₹124 crores for DelhiMeeru­t Expressway were pending to be disbursed to farmers. The official sources said that this had led farmers to stage protests and stall work often.

“Apart from this, there were nearly 900 arbitratio­n cases and most of these have been decided by the executive court of the DM while some are pending in judicial court,” she added.

Under the jurisdicti­on of Ghaziabad district, the National Highways Authority of India (NHAI) had to construct nearly 24.5kms of EPE project and the work often got stalled by farmers. The villagers have also demanded a service lane over the entire stretch of the expressway and the issue is yet to be fully decided on.

The apex court had earlier asked the Uttar Pradesh director general of police to provide security for the constructi­on work of the expressway (EPE) as the work was stopped by farmers.

The NHAI had earlier told the Supreme Court Bench that no constructi­on was being carried out in the 25-km stretch in Ghaziabad due to protests by farmers and lack of police protection, despite the apex court’s order. The officials now stated that the work has resumed and the pending issue of the service will be resolved as per NHAI guidelines.

 ??  ??