Metro’s longest line will run in two parts, 4 km stuck over rehab delay of evicted people

- Faizan Haidar faizan.haider@hindustant­imes.com

Direct metro connectivi­ty between a major part of east Delhi with southern parts of the city has been delayed further because Delhi Metro’s longest line – the 58.6-km MukundpurS­hiv Vihar corridor -–will operate in two segments as a small part of the line is stuck over land issues.

This line will connect north and west Delhi with south and east Delhi. But about 4 km is stuck over land acquisitio­n and rehabilita­tion of affected people in east Delhi’s Trilokpuri.

The Delhi Metro Rail Corporatio­n (DMRC) has to rehabilita­te 108 families but is falling short of land. Only 66 families can be accommodat­ed on the plot it has been alloted for the purpose.

It has requested the Delhi government for more land but the process will take time, which means constructi­on on that 4-km stretch will not be over before the end of 2018.

“In Trilokpuri, we are not able to accommodat­e all these people on the piece of land given to us. This is because the available land for the dwellings has reduced as the road width had to be increased. We have asked for additional land from the Delhi Urban Shelter improvemen­t Board (DUSIB), DMRC chief Mangu Singh said.

“We do not know how much time it will take so we will leave that part. Trains coming from Mukundpur will be reversed from Mayur Vihar pocket 1 station while those operating from Shiv Vihar will return from IP extension . We are hopeful it will be resolved soon,” Singh said.

DMRC hopes to open rest of the portion by March 2018. But passengers from east Delhi areas such as Shiv Vihar, Welcome and Krishna Nagar will have to use Anand Vihar as an interchang­e to go to south Delhi or Gurgaon The Delhi Metro Rail Corporatio­n (DMRC) has to rehabilita­te 108 families. But, has now been told that only 66 families can be accommodat­ed on the land given for the purpose.

It has requested the Delhi government’s slum agency — Delhi Urban Shelter Improvemen­t Board (DUSIB) for more land and the process will take time, which means the constructi­on on the 4-km-stretch will be delayed.

The scheduled launch of the entire line was December 2016. It may not start before the end of 2018.

and Faridabad.

Once the entire line is complete, they can commute to Lajpat Nagar and INA directly, without going to RajIv Chowk.

The entire line was scheduled to be launched by December 2016. This stretch also provides crucial connectivi­ty to the depot but DMRC will manage parking of trains by taking them all the way back to the origin stations.

The DUSIB had allotted a 11,138 square metre plot to DMRC in front of blocks 15, 16, 17 and 18 in Trilokpuri to relocate affected persons. But due to resistance from local residents, work could not begin at the plot on time.

The residents had moved court but the judgment went in favour of DMRC. Work in this section started in August, 2013. DMRC will take a year and a half to complete the relocation work. Constructi­on of a viaduct at the affected portion will begin after the residents shift to their new accommodat­ion.

“Constructi­on of 108 houses for shifting affected persons of Trilokpuri block 15 started on October 13, 2016 as per the Delhi High Court’s direction. The DDA said the right of way in front of these quarters is 30 metres. But the width of the existing road is 21 metres. The DDA plans to

develop Sanjay Lake and a commercial complex, which will increase traffic. So the road will be widened by taking nine metres from the plot given to DMRC. So only 66 quarters can be constructe­d on the remaining land,” a DMRC official said.

For the remaining 42 residents, the DMRC has asked for a 2,615 square metre land in front of Block-14, Trilokpuri.

With 10 interchang­e stations, the line was set to take off load existing ones, especially Rajiv Chowk. “The line is constructe­d in a way that it will decongest all the other lines,” said a DMRC official. Open manholes killed 167 persons and injured five in 2015. Uncovered, unprotecte­d ‘trenches, ‘nallas ‘ and pits took an even heavier toll--as many as 730 fell into them during the year. While 663 died, 65 suffered injuries. In the previous year, 195 persons died by falling into open manholes, while 780 died on account of accidental fall into open pits, says National Crime Records Bureau data.

Behind each of these tragic deaths is a tale of callous indifferen­ce exhibited by the municipal authoritie­s to the safety of the citizens and to the duty of care entrusted to them. If only these authoritie­s had done their job and closed the death traps on roads and pavements, so many lives would not have ended. The death of a gastroente­rologist

TRILOKPURI TANGLE Metro rail has to rehabilita­te 108 families but can accommodat­e only 66 on the available plot of land; DMRC has now requested Delhi govt to allot more land

 ??  ??
 ??  ??