Noida Metro’s Aqua line may begin in Sept

- Snehil Sinha snehil.sinha@htlive.com

NOIDA: The Noida Metro’s aqua line, connecting Sector 52 with Knowledge Park in Greater Noida, is expected to start functionin­g by September, officials said on Saturday.

While trial runs of the available coaches have been going on since January, the Research Design and Standards Organisati­on (RDSO), the nodal agency nominated by the ministry of Railways for the conduct of oscillatio­n trials, will begin inspection­s in the third week of May.

A meeting of senior officials from the Delhi metro rail corporatio­n (DMRC), the Noida metro rail corporatio­n (NMRC), the Noida Authority and the Yamuna Expressway Industrial Developmen­t Authority (Yeida) took place on Saturday to review the progress of the aqua line.

Officials said that while the first 10 kilometre-stretch from Depot Station to Sector 147 had been handed over by the DMRC to the RDSO for oscillatio­n trials, the remaining 20 kilometres would be ready in the next couple of months. The RDSO’S trials for the first stretch would begin in the third week of May and were expected to be completed in a fortnight, said officials.

“We hope the line will become operationa­l by August-september. Trials are on since January and progress rate along the line is good,” Mangu Singh, managing director of DMRC, said.

Officials said that inspection by the commission­er for metro rail safety and other required clearances would be the next major milestone.

A total of 11 trains are required to start commercial operations immediatel­y. As on date, three trains are already undergoing extensive testing, while the next three trains are expected to be delivered at the depot in June.the remaining trains are expected to be delivered timely, according to NMRC officials.