Ashram woes deepen after 2 days of rain

- Pankhuri Yadav pankhuri.yadav@hindustant­imes.com

Heavy rain for the past two days has added to the endless cycle of chaos at Ashram Chowk in the form of deeper potholes and loose mud, adding another degree of pain that hundreds of thousands of commuters have to endure while passing through this important road intersecti­on.

A site visit by HT on Wednesday showed how the already worn out road surface at the intersecti­on has worsened due to rains, and the constructi­on material dumped on the roadside has flown on to the road as slush that is making it even more difficult for the motorists to negotiate the stretch.

The Delhi government’s public works department (PWD) began constructi­ng an underpass, aimed at decongesti­ng the transport heavy stretch, in December 2019. HT reported on August 17 that, having missed four deadlines already, the

NEW DELHI:

PWD has fixed a new Decemberen­d deadline for the project. However, as constructi­on work continued at a snail’s pace, pathetic site management has ensured that the stretch has remained a traffic nightmare for nearly two years now. Simultaneo­us work on extending the Ashram flyover on Ring Road has expanded the chaos from all four directions at the main intersecti­on to Maharani Bagh.

Ashram, which connects south and central Delhi and virtually serves as the link between two NCR cities — Noida and Faridabad — sees over 350,000 vehicles passing every day during peak rush hours in the mornings and evenings.

A PWD official said they will complete the first phase of the project by the end of 2021. “We have received complaints about potholes. We used to fill those up before the monsoon, but no road repair work can be done during rains,” said a senior official.

Department officials said both the underpass and the flyover extension projects were hit by multiple setbacks in the last two years.

“Delhi has received record rainfall in the past two days. It is because of the monsoon preparatio­ns and precaution­s taken by the Delhi government in the past few months that the infamous Minto Bridge did not witness waterloggi­ng to the extent of a bus getting inundated. Apart from this, it was observed there was no waterloggi­ng in several other parts of the city as well,” said a state spokespers­on.

Commuters rued that there was no end in sight to their daily travails.

“Whenever it rains, it becomes a nightmare to cross this area. PWD is not doing anything to fix it. I have often read about the deadlines of this project in newspapers, but the work is yet to be completed. What will happen if a mishap occurs due to these potholes?” asked Gagandeep Singh, who travels from central Delhi’s Gol market to Faridabad for work.

From Nizamuddin

Ongoing underpass project

Nehru Nagar

M

Existing flyover

Friends Colony

Mathura

Road

From Shaheen Bagh

Ring Road

Ongoing flyover extension Maharani Bagh