Hindustan Times (Delhi)

Work on C Vista avenue to wrap up by June-end

- Risha Chitlangia

NEW DELHI: The deadline for the completion of the Central Vista Avenue has been extended by a month from the end of May to the end of June, said two Central Public Works Department (CPWD) officials aware of the developmen­t who asked not to be named.

CPWD officials said that while major constructi­on work is over, that on the underpasse­s and amenity blocks is still going on.

A senior CPWD official said: “The structure of the four pedestrian underpasse­s and eight amenity blocks along Rajpath is over, but the cladding work is going on. Of the two plazas at the C-hexagon at India Gate, one is ready while the other is nearing completion. We are also constructi­ng eight vending plazas. The work will be completed by June end.”

CPWD, which is executing the project, said that the constructi­on work at the site resumed in February, after Republic Day, for which special arrangemen­ts were made.

For the parade, temporary structures were erected in the lawns and heavy machines were used to complete the work, which left the water sprinkling infrastruc­ture partially damaged, said a second senior CPWD official aware of the developmen­t.

“The avenue was dug up at some locations to repair the damage caused to the water sprinkling system due to movement of heavy vehicles during the preparatio­n of the parade. In January, some stopgap arrangemen­ts for parking etc were made for the parade,” added this person.

The redevelopm­ent of the ₹608-crore Central Vista Avenue, part of the Centre’s ₹13,500 crore Central Vista redevelopm­ent project, started in February last year. Under the project, Rajpath and the area along it between Vijay Chowk to India Gate is being redevelope­d.

The project’s initial deadline was December-end.

Work on the project involves the constructi­on of four pedestrian underpasse­s, eight amenity blocks, relaying of Rajpath and constructi­on of pathways along it and in the lawns, improving the canals and constructi­ng 16 permanent bridges over them, and the constructi­on of undergroun­d utility ducts for electric and other cables etc.

CPWD officials said that they faced many challenges in completing the work. “The pace of work was affected due to the second and third waves of Covid. Work had to be stopped due to unpreceden­ted rain last year. For the Republic Day parade, special arrangemen­ts were made and then we restarted the work. It took some time to mobilise resources,” said the second CPWD official.

The Union housing and urban affairs minister didn’t comment on the matter.

 ?? PTI ?? CPWD, which is executing the project, said that the constructi­on work at the site resumed in February, after Republic Day.
PTI CPWD, which is executing the project, said that the constructi­on work at the site resumed in February, after Republic Day.

Newspapers in English

Newspapers from India