Hindustan Times (Jammu)

Outer Ring Rd’s Mukarba Chowk underpass delayed

- Paras Singh letters@hindustant­imes.com

The deadline to finish an underpass that was aimed at decongesti­ng the busy Mukarba Chowk on the Outer Ring Road-GT Karnal Road intersecti­on has been pushed back by six months, senior PWD officials said on Thursday. The project that was to be completed by June this year, will now be finished by December, the officials said.

According to the project’s progress report for the month of March, land acquisitio­n from the Irrigation and Flood Control (I&FC) department has delayed the work further even as the shifting of the gas pipelines has been completed and high-tension wire was being done. “The payment to the power distributi­on company has been made in December. Acquisitio­n of land from Irrigation and Flood Control department is to be expedited,” the report said, a copy of which HT has seen.

The Mukarba chowk underpass is being built near Gate number 3 of Haiderpur-Badli Metro station to facilitate pedestrian­s and nonmotoris­ed vehicles. It is nine metres wide — five metres for nonmotoris­ed vehicles and four metres for the pedestrian­s. Currently, vehicles from Badli towards Shalimar Bagh on Outer Ring Road have to use a loop on the main Mukarba Chowk. With the new underpass, the vehicular load on the main intersecti­on will be reduced.

The project was expected to be completed in a year after its foundation stone was laid down by the then-PWD minister Manish Sisodia on September 27, 2022. The deadline was later pushed to June 2024. On July 7, lieutenant gover

Officials said land disputes with I&FC and utility transfer issues have delayed the project

INITIAL DEADLINE: OCTOBER 2023

FromPitamp­ura

OUTERRINGR­OAD

FromJahang­irpuri

NEW DEADLINE: DECEMBER 2024 PUSHED BACK BY 6 MONTHS

Max Wali road

Obstacles project ran into

PWD requested I&FC for land in Sept 2022 and started constructi­on in anticipati­on of the transfer. However, I&FC filed a police complaint over the constructi­on. The land was finally transferre­d in July 2023. The PWD now says that acquisitio­n is still underway and needs to be expedited Undergroun­d natural gas pipelines passed along the alignment of the underpass; IGL finally completed the transfer and the lines were cleared in December 2023 Expenditur­e on transfer of power lines was finalised in September. Payment was made to discom on December 22, 2023 to complete the relocation

nor (LG) VK Saxena had approved the transfer of 1.2-acre land from the I&FC department to PWD, after a delay of 11 months. The revised deadline now stands at December 2024.

A PWD official quoted above said, “A large number of undergroun­d power lines and natural gas lines were passing along the alignment of the underpass. The gas lines were shifted by IGL last year on November 28, and the payment for the shifting of power lines has been made to the power company on December 22, and it is expected to be completed soon. We are now trying to expedite the documentat­ion for the land acquisitio­n.”

HT reached out to Delhi government spokespers­on, who did not comment on the further delay in the project.

Mohit Aggarwal, 36, a resident of Shalimar Bagh said that the area is a mess due to heavy traffic jams at Mukarba Chowk. “The whole intersecti­on is a mess. During evening, the traffic jams on GT Karnal road extend up to Swaroop Nagar,” he added.

Ashutosh Rana, a commuter who regularly moves between Pitampura and Kashmiri Gate, said, “Due to the two constructi­on projects, the traffic goes into a tailspin. If the underpass was ready, hours of travelling time could have been saved every day.”

 ?? ??
 ?? ??
 ?? ??