Hindustan Times (Lucknow)

Environmen­t norms ignored; vigilance or CBI probe likely

- Umesh Raghuvansh­i uraghuvans­hi@hindustant­imes.com

LUCKNOW: A CBI or vigilance department probe may be the only option before the state government as a panel begins examining the judicial committee report that indicted two IAS officers and others for implementa­tion of Gomti River Front project without looking into environmen­tal aspects properly.

Chief minister Yogi Adityanath had constitute­d a judicial committee to look into irregulari­ties in the Rs 1,503-crore project when it was found that only 60 per cent work had been carried out despite an expenditur­e of Rs 1,435 crore (95% of project cost).

The three-member committee, headed by retired high court judge AK Singh with IIM professor AK Garg and BHU’s retired professor UK Chaudhary as members, submitted its report early this month.

To examine the report and recommend action, the government has constitute­d a fourmember committee headed by state minister for urban developmen­t Suresh Khanna.

The 80-page inquiry report has reportedly indicted the then chief secretary Alok Ranjan, then principal secretary, irrigation, Deepak Singhal and others for gross irregulari­ties in implementa­tion of the project.

Taking exception to the implementa­tion of the project without appropriat­e environmen­t clearance, the report said, “As per the wishes of Mr Chaudhary (member, inquiry committee), the discussion­s held by members on various points (page numbers 58-68) show that the project was neither examined on environmen­t point nor any such examinatio­n was carried out despite special orders from the then chief minister (Akhilesh Yadav) through letter dated August 31, 2015.”

“The then executive engineer, superinten­ding engineer, chief engineer, chairman of monitoring committee, principal secretary, irrigation appear to be responsibl­e for gross negligence,” the report added.

Ranjan led the monitoring committee constitute­d to oversee the implementa­tion of the project. According to sources, the inquiry committee has raised serious questions on Ranjan’s role as chairman of the monitoring committee.

Sources said the judicial committee closely examined the documents available with the irrigation department and held all the engineers, including the chief engineer, responsibl­e for the delay in 24 project works.

“Keeping in view the size of the project, a high-level monitoring committee was constitute­d for the purpose (to check the delay) with the then chief secretary (Alok Ranjan) as chairman and comprising the then principal secretary, irrigation, (Deepak Singhal), chief engineer, head of irrigation department and other engineers as members,” the judicial committee report said.

“The monitoring committee held 23 meetings in two years. But for all these points mentioned in this report, the committee’s chairman and members are prima facie guilty,” the report observed.

The inquiry committee has taken note that Ranjan had written to Singhal to act on the CM’s letter and submit a report to him in a week.

The committee has also raised questions on the lack of transparen­cy in tendering process, purchases at higher rates and financial irregulari­ties for not depositing the amount received from auction of sludge.

“Only VK Niranjan, the then executive engineer, got the sludge auctioned and deposited Rs 19 lakh,” the committee noted.

Meanwhile, Ranjan said he had not seen the inquiry report and would not like to comment on the issue.

“Such issues – irregulari­ties in tendering process and high rates for purchases – do not come for the chief secretary’s approval. The monitoring committee’s role was to see the implementa­tion of the project as per schedule. Expenditur­e finance committee (EFC) granted financial approval to the projected which was headed by the then principal secretary, finance (Rahul Bhatnagar), who now holds the office of chief secretary,” he said.

Singhal was not available for his comments.

The inquiry committee has, however, given a clean chit to Bhatnagar in the report. “It (the conclusion­s) is not about the present chief secretary (Rahul Bhatnagar) and present principal secretary, irrigation, (Suresh Chandra) because very few meetings took place after June 2016 and at that point this work was nearing completion,” the report said.

“Nothing much could have been done in the last phases as the reins were loose since the beginning. They could not have done anything at this stage even if they wanted to,” it added.

Sources said the EFC, headed by Bhatnagar, had brought down the cost of project from Rs 1,990 crore to Rs 1,503 crore during a meeting on June 10, 2016.

The EFC had also advised that no financial or administra­tive sanction be issued for the project without seeking approval from the state cabinet. It asked the irrigation department to seek environmen­tal clearances before going ahead with the implementa­tion of the project.

Newspapers in English

Newspapers from India