Hindustan Times (Lucknow)

METRO’S ‘GROUNDBREA­KING’ MOMENT

Tunnel boring machine ‘Gomti’ emerges in front of Sahu Cinema

- Anupam Srivastava anupam.srivastava@hindustant­imes.com

Lucknow Metro workers

(in pic) celebrate after the tunnel boring machine completed its first ‘deep-dig’ from Bapu Bhawan to Hazratganj (812 metres), in Lucknow on Monday.

History was created when LMRC’s tunnel boring machine (TBM), ‘Gomti’, emerged in Hazratganj on Monday after making an 812-metre tunnel from Bapu Bhavan to Sahu Cinema.

The TBM had began its journey on January 23, 2017. In just six and a half months ‘Gomti’ covered the Bapu Bhavan-Sahu Cinema distance at the rate of 8.4 metres per day.

Jubilant over the achievemen­t, the LMRC staff danced and clicked photograph­s with the Tricolour in their hand when the TBM roared out of the tunnel.

LMRC MD Kumar Keshav said, “The Lucknow Metro Rail Corporatio­n has achieved one of the biggest milestones in the form of completion of first TBM drive in the constructi­on of undergroun­d metro in Uttar Pradesh. Now, the focus is on dedicating the priority section from Transport Nagar to Charbagh to the public as soon as possible.”

“Hazratganj is the main market of the city and no one would have thought of undergroun­d metro network in the busiest market five years back. I thank all the traders and people of Lucknow who cooperated with the LMRC for the work in the area,” he said.

He added, “The state-of-theart on-board computeris­ed tunnel guidance system has been provided in TBMs to ensure that tunnelling is done as per the designed alignment with the highest level of accuracy. Extensive instrument­ation has been done throughout the undergroun­d stretch and continuous online and real- time monitoring is done by a team of dedicated experts to ensure safety during TBM operation.”

The 3.67-km undergroun­d stretch of Lucknow metro project starts immediatel­y after Charbagh and covers three undergroun­d stations at Hussaingan­j, Bapu Bhavan Sachivalay­a and Hazratganj.

The work of tunneling in this section was started from the Sachivalay­a undergroun­d metro station using two tunnel boring machines (TBMs) named –‘Gomti’ and ‘Ganga’ for Up and Down lines respective­ly.

“The tunneling in this stretch posed a big technical challenge as the route passes beneath highly congested areas and basements of commercial establishm­ents. Laying tracks at a depth of 12-25m below ground level was a big challenge. LMRC has accomplish­ed the difficult mission of not affecting the working of commercial establishm­ents even for a day while tunneling beneath them,” said Keshav.

The 75-metre-long tunnel boring machine ‘Gomti’ took about six and a half months to complete tunnelling of 812 m length from Sachivalay­a to Hazratganj metro station.

The tunnel boring machine will be taken out as it will start digging the tunnel from Bapu Bhavan to Hussaingan­j within a few days.

The second TBM ‘Ganga’, which is working Down Line between Sachivalay­a and Hazratganj, has completed 782 m tunnelling and its breakthrou­gh is also expected shortly.

 ?? SUBHANKAR CHAKRABORT­Y/HT ??
SUBHANKAR CHAKRABORT­Y/HT
 ??  ??
 ??  ??
 ?? HT PHOTOS ?? Clockwise from top: Sequence of pictures showing the breakthrou­gh by the TBM in Ganj
HT PHOTOS Clockwise from top: Sequence of pictures showing the breakthrou­gh by the TBM in Ganj
 ??  ??

Newspapers in English

Newspapers from India