Hindustan Times (Lucknow)

Rail that became a reality in record time

NOTCHING UP A MILESTONE The 8.9km priority corridor completed in 33 months. Unwavering support from different govt department­s played crucial role in Metro project meeting deadline

- Anupam Srivastava anupam.srivastava@hindustant­imes.com

LUCKNOW: The state capital is set to notch up a milestone with the roll-out of Metro rail service . But what will also go down in history is the fact that phase-1 of the gigantic project became a reality in record time.

The completion of the 8.9-km priority corridor in 33 months drew acclaim from one and all. Officials claimed no other project in Lucknow had ever been completed before the deadline and insisted that perfect planning and the execution helped Team Metro accomplish the task.

“It could not have been possible without unwavering support from the then state and central government,” said an official while revealing that as many as 250 clearances from different department­s of state and central government­s had to be taken in the process. It is significan­t, as delay in one clearance would have meant the project losing months.

MAJOR CHALLENGES

While it was in August 2014 that the civil contract was finalized, the work began in September. Before actually starting the work, the LMRC did a lot of public interactio­n.

“It was to record the opinion of the people so that the project can be done according to their wishes. It was because of this feedback that people supported Metro at every step despite the fact that they themselves faced a number of hardships,” said MD LMRC Kumar Keshav.

“Utility identifica­tion was a big issue. The entire city had already been utilised for the road purpose and there were narrow footpaths and congested buildings. The LMRC had the challenge of widening some of the footpaths, removing some of the electrical poles, electrical cables and some telecoms and water pipelines from one place to another. Besides, encroachme­nt on roads was a big problem,” he said.

Since the city had never seen this type of work being done on busy roads, the LMRC had to face big challenge in terms of taking people and small utility agencies together. The fact that the utilities were scattered and some of the designs and drawings of power cables and pipelines were missing, it became all the more difficult to pinpoint their presence at the desired spot.

“We took the help of utility agencies and are thankful to them as they supfor ported us despite LMRC being new to them. Gradually, people developed their confidence in us and we shifted the utility zone on their behalf,” said Keshav.

ADMN BACKING

With coordinati­on in place and priorities defined, the delays were controlled and contractor­s were given a clear zone to work within a strict time-frame. “All the issues that cropped up were taken care of and work was executed meticulous­ly with the help of administra­tive backing from the government,” said Keshav.

PERFECT EXECUTION

LMRC maintained proper barricades; deployed their own marshals and trained them with the help of local police to control traffic. Weekly monitoring of activities was being done and the state government was kept updated all the time. Meticulous planning and implementa­tion was controlled at every level.

Strict time frame was a challenge but close monitoring ensured that things kept moving. Baseline time diagram was made in the beginning.

INFRASTRUC­TURE CHALLENGE

In a big city, infrastruc­ture capabiliti­es like big machinery, capable contractor­s, good vendors, materials etc are available constructi­on but in an upcoming metro city like Lucknow, these technologi­es were not available. Most of the things LMRC started working with were outsourced from outside the city.

LAND REQUIREMEN­T

As far as the land requiremen­t and land acquisitio­n was concerned, the LMRC tried to reduce the private land requiremen­t to the bare minimum. The government issued notificati­on and orders for the LMRC for direct negotiatio­n with private parties, which was not required in most of the cases.

A big challenge faced by the LMRC was of Avadh Rotary span where a statue of Dr Bhim Rao Ambedkar was installed and that rotary was to be narrowed.

This crossing was not a simple crossing as it would have resulted in political problem. But this was handled properly by administra­tion with the help of state government. Not only that, all the political parties supported Lucknow Metro as it will serve all the residents.

FUNDS NEVER A PROBLEM

Besides that, funds were never the problem as state and centre ensured that all the loans from bank were released on time and aid from them kept coming on time.

Newspapers in English

Newspapers from India