Hindustan Times (Lucknow)

Metro project: Tunnel work from Charbagh to Hussaingan­j complete

LMRC finished 3.67km tunnel work in just 15 months: Kumar Keshav

- HT Correspond­ent lkoreporte­rsdesk@hindustant­imes.com ▪

LUCKNOW: The Lucknow Metro Rail Corporatio­n (LMRC) achieved a milestone when tunnel boring machines (TBMs) – ‘Ganga’ and ‘Gomti’ simultaneo­usly broke through the ground face to reach the Hussaingan­j undergroun­d Metro station after completing their third and final drive between the Charbagh and Hussaingan­j undergroun­d Metro stretch on Saturday.

With this, the tunnel work from Charbagh to Hussaingan­j is complete.

Earlier also, these two TBMs had completed the tunneling drives between the Bapu Bhavan - Hazratganj and the Sachivalay­a-Hussaingan­j Metro stretch in record time.

The Lucknow Metro Rail Corporatio­n had completed the tunnel work of 3.67 km in a record time of just 15 months, said Kumar Keshav, MD, Lucknow Metro Rail Corporatio­n (LMRC). He said the tunnel work had been completed two months ahead of schedule.

“LMRC had started its first tunneling drive from the Bapu Bhavan Metro station on January 18 , 2017 and tunnelling for the whole section was scheduled to be completed by June, 2018 but it has been completed two months ahead of the schedule, credit for which goes to the entire team . Enormous technical and logistical challenges were met with hard work by engineers of LMRC and the Gulermak-TPL JV (the contractor),” he said.

“Tunnelling through the heart of the city posed an enormous engineerin­g challenge as the route passed beneath highly congested areas and basements of commercial establishm­ents. Realizing the enormity of the technical challenge, engineers working on the project carefully planned each and every step in tunneling operation. The final drive from Charbagh to Hussaingan­j was the most challengin­g wherein TBMs had to pass just 1m below the bed of Haider Canal near a highly populated area with dilapidate­d hutments on weak foundation­s.”

The engineers faced major technical challenges during the final drive, including very hard strata which significan­tly

reduced the TBMs advancemen­t rate and also posed a critical challenge towards the safety of the TBMs.

Kumar Keshav said, “The state of the art onboard computeriz­ed tunnel guidance system provided in TBMs ensured that the tunnelling was done as per the designed alignment to the highest level of accuracy. Extensive instrument­ation was done throughout the undergroun­d stretch and continuous online and real time monitoring ensured by a team of dedicated experts for safety during TBM operations.”

 ?? ASHOK DUTTA / HT ?? ▪ The project site at Hussaingan­j, Lucknow.
ASHOK DUTTA / HT ▪ The project site at Hussaingan­j, Lucknow.

Newspapers in English

Newspapers from India