Delayed by 8 months, Metro’s longest line to open next Aug

Hurdles in 5-km stretch connecting depot pushes back deadline

- Faizan Haidar faizan.haider@hindustant­imes.com

NEW DELHI: Delhi Metro’s longest line — the 58.59 km MukundpurS­hiv Vihar corridor which will connect north and west Delhi with south and eastern parts of the city — will be delayed by at least eight months and will be launched in August 2017.

The line was scheduled to be launched in December 2016, but delay in getting land in east Delhi’s Trilokpuri and expansion of National Highway-24 delayed the project.

Though the two factors are affecting only a 5-km stretch of this line, this portion provides crucial connectivi­ty to the Vinod Nagar depot where the coaches will park, without which it would not be possible to start the line.

“The constructi­on work is in its last leg but with no connectivi­ty to the depot, we won’t be able to start the line for passengers. We can conduct trial runs in patches but passengers will be able to use the line only after we have the link to the depot ready,” said a Delhi Metro Rail Corporatio­n (DMRC) official.

The elevated alignment of the corridor passes over National Highway-24 towards Ghaziabad at two locations – between Vinod Nagar and Vinod Nagar East and between IP Extension and the Vinod Nagar metro depot.

The DMRC had begun work on these sections after obtaining clearance from the ministry of road transport and highways in March 2013. In June 2014, the National Highways Authority of India (NHAI) informed DMRC that there should not be any metro structure within 90 metres of right of way (ROW) on National Highway-24 as the road was now a part of the Meerut Expressway project.

In September 2014, a decision was taken in a meeting between DMRC and NHAI to accommodat­e the metro proposal. In subsequent meetings, the issue of providing adequate vertical clearance above highways was discussed and an agreement was reached. Constructi­on work started again with the ministry’s permission.

But in January 2015, NHAI again issued a stop work letter to DMRC and said the horizontal location of the piers on NH-24 was coming in way of the proposed carriagewa­y.

In June 2015, the ministry of road transport and highways held a meeting with organisati­ons to find a solution. After obtaining all clearances again, DMRC finally begun work in March 2016.

With no work for almost two years, the line will be delayed. DMRC had erected six pillars and now is in the process of dismantlin­g four of them.

Then, locals in Trilokpuri had moved court as they did not want to be relocated because of the metro line. The court has now asked DMRC to rehabilita­te them.

“The location of pillars have been decided and work on the new plan has started. There has been a slight change in the route but our team has managed it well. We have got land in Trilokpuri and work will begin,” the official added.

 ?? RAVI CHOUDHARY/HT ?? Two pillars built on either side of NH-24 at Ghazipur for the constructi­on of Mukundpur-Shiv Vihar line were dismantled.
RAVI CHOUDHARY/HT Two pillars built on either side of NH-24 at Ghazipur for the constructi­on of Mukundpur-Shiv Vihar line were dismantled.