- Press Trust of India letterschd@hindustant­imes.com

NEW DELHI : The National Green Tribunal (NGT) has imposed a cost of Rs 1 lakh on the Punjab Pollution Control Board (PPCB) for a long, unexplaine­d delay in compliance of its order with regard to an industry in Barnala.

A bench headed by NGT chairperso­n justice Adarsh Kumar Goel said no explanatio­n has been furnished by the officer representi­ng PPCB except for orally stating that the board has been issuing directions to the industry.

The tribunal was hearing a plea filed by Beant Singh Bajwa, president, National Anti-Corruption Council, against violation of environmen­tal norms by Trident Factory, Dhaula, Mansa Road, Barnala.

The tribunal noted that no direction has been produced nor there is any explanatio­n as to why adverse measures were not taken against the erring factory.

The NGT said it is surprising that the PPCB has failed in securing compliance, as directed, by taking necessary preventive and remedial measures in exercise of its statutory powers under the Water (Prevention and Control of Pollution) Act, 1974, Air (Prevention and Control of Pollution) Act, 1981, and Environmen­t (Protection) Act, 1986.

“In view of long unexplaine­d delay on the part of the PPCB in complying with the orders of this tribunal, we impose a cost of Rs 1 lakh which may be deposited with the Central Pollution Control Board within one month, which will be personal responsibi­lity of the member secretary, PPCB. The pollution control board is free to recover the same from the erring officers,” the bench said.