UPERC’s deadline for meters may be a tall order in poll year

Power personnel in UP are very sensitive to the issue of metering of their residences and have strongly and successful­ly opposed attempts in this regard in the past

- Brajendra K Parashar bkparashar@hindustant­imes.com

LUCKNOW: Taking a serious view of non-implementa­tion of its earlier directions on installati­on of energy meters on the premises of power personnel till date, the UP Electricit­y Regulatory Commission (UPERC) has set a deadline for UP Power Corporatio­n Ltd (UPPCL) to complete the task by the end of the current financial year.

“The commission directs that metering of LMV-10 connection­s should be completed by end of FY 2021-2022,” the commission said in its tariff order issued on Thursday. The LMV-10 category refers to the unmetered power staff.

People familiar with the issue, however, said the regulator’s directions were most likely to be honoured in the breach only this time also in view of the assembly elections early next year.

“Considerin­g the fact that there are assembly polls early next year, it is impossible for the state government to give a go-ahead to the UPPLC to install meters on the powermen’s premises and invite their wrath,” a senior energy department official said.

The powermen in UP are very sensitive to the issue of metering of their residences and have strongly and successful­ly opposed attempts in this regard in the past despite the fact that UP is believed to be the only state where power employees and pensioners enjoy the luxury of using unmetered and unaccounte­d electricit­y.

UPERC, in November 2017, abolished LMV-10 category, putting consumers in this category at par with any other domestic consumer categorise­d as LMV-1 for the purpose of billing. The move implied that the UPPCL was supposed to charge the same tariff from unmetered power personnel as applicable to unmetered domestic consumers.

This step, however, did not achieve the purpose and the UPPCL/discoms failed to provide any informatio­n to UPERC on the number of meters installed on the power staff’s residences whenever it sought details on the subject.

“Despite repeated directions of the commission, the same (installati­on of meters) has not been done by the licensees,” the commission observed in Thursday’s tariff order and fixed a higher tariff for them so that it would act as a disincenti­ve to using unmetered power.

“Hence, the commission is forced to re-compute the revenue for LMV-10 consumers (power staff) considerin­g the average consumptio­n per consumer per month to be 700 units and at Rs 7.00 / kWh (the rate of LMV-1, other metered category – highest slab),” the regulator ordered and clarified that the revenue deemed to have been realised from would be added to UPPCL’s final revenue realisatio­n and same would be taken into view while revising the tariff in future.

For the power staff, based on the balance sheet data and past trend, the commission has computed deemed revenue of Rs. 61.05 crore, Rs 70.18 crore, Rs 55.28 crore and Rs 140.68 crore of the state discoms namely DVVNL (Dakshinanc­hal Vidyut Vitaran Nigam Ltd), MVVNL (Madhyancha­l Vidyut Vitaran Nigam Ltd), PVVNL (Paschimanc­hal Vidyut Vitaran Nigam Ltd) and PuVVNL (Purvanchal Vidyut Vitaran Nigam Ltd) respective­ly.

As per the data provided by UPPCL to the regulator, there are 98,218 power men consuming unmetered electricit­y at their residences with their total electricit­y load having been estimated to be 4,15,912.88 KW. The power personnel together consumed 577.52 million units of electricit­y in 2020-21, according to the data.