Hindustan Times (Ranchi)

Bihar to get 402 MW more power as NTPC readies unit 2 of Barh plant

- Ruchir Kumar ruchirkuma­r@hindustant­imes.com

AT PRESENT, NTPC’S POWER ALLOCATION TO BIHAR IS 5,361 MW AGAINST ITS PEAK LOAD DEMAND OF 6,500 MW

PATNA: Bihar will get 402 MW of additional power, as the National Thermal Power Corporatio­n Limited (NTPC) on Saturday evening completed the boiler light-up test of its second unit of 660 MW, taking a crucial step toward commission­ing its stage I project of the Barh super thermal power plant (STPP), said NTPC officials.

At present, the NTPC’s power allocation to Bihar is 5,361 MW against its peak load demand of 6,500 MW (approx).

The test signifies the readiness of the boiler for the power generation process, said the officials. “However, commercial generation of power from this plant would begin anytime in this financial year, the date for which has not been finalised yet,” the official said.

“We have to now do steam blowing, which is to check the optimum pressure of steam the boiler can handle to run its turbine. After that, the plant has to be synchronis­ed with the national grid as well as the other automated controls of our power generation system. We will then proceed with its commission­ing, which involves a trial run of the plant up to 72 hours at efficiency above the installed capacity of the power plant (above 660 MW in the instant case),” the spokespers­on added.

Thereafter, the NTPC will commence work on the commission­ing of unit 3 of stage I.

“Erection activities of unit 3 of stage I are at an advanced stage. We are hopeful to meet our deadline of completing commercial generation of the plant by December 2023,” said the spokespers­on.

The Barh STPP project, the foundation stone of which was laid by the then Prime Minister late Atal Bihari Vajpayee on June 5, 1999, will be complete after unit 3 of stage I begins commercial generation of power by end of 2023.

The Barh STPP project has an installed capacity of 3,300 MW, of which stage I is of 1,980 MW (3 x 660 MW unit each) and stage II of 1320 MW (2 x 660 MW unit each).

Bihar gets 90.8% power (1,198.6 MW out of 1,320 MW) from stage II and 60.91% power (401.98 MW out of 660 MW) from stage I of the Barh STPP project.

Initially, the project was of 1,980 MW only. However, the delay in execution of the project by Technoprme­xport, a Russian firm, awarded the work on March 14, 2005, led to conceptual­isation of stage II of the project, which was completed on February 18, 2016, after the successful commercial generation of unit 5. Its unit 4 began commercial operation on November 15, 2014.

Unit 1 of 660 MW of stage I of the Barh STPP became commercial­ly viable on November 12, 2021. Bihar gets 402 MW of power from it.

The boiler light-up of unit 2 was completed on Saturday and is expected to commence commercial generation of power during this financial year. Unit 3 of stage I is lined up for commercial operation by end of December 2023.

Inordinate delay in execution of work for stage I, led to the terminatio­n of the contract of the Russian firm on January 14, 2015, almost a decade after it was awarded the work on March 14, 2005.

The balance work of steam generators and auxiliarie­s was subsequent­ly awarded to Doosan Power Systems India on January 14, 2015. Work has since been progressin­g almost as per the schedule, said NTPC officials..

Newspapers in English

Newspapers from India