Hindustan Times (Ranchi)

443 INFRA PROJECTS HIT BY ₹4.92 L CR COST OVERRUN IN FEB

- Press Trust of India

As many as 443 infrastruc­ture projects, each entailing an investment of ₹150 crore or above, were hit by a cost overrun of more than ₹4.92 lakh crore in February 2024, an official report stated.

According to the Ministry of Statistics and Programme Implementa­tion (MoSPI), which monitors infrastruc­ture projects worth ₹150 crore and above, out of 1,902 projects, 443 reported cost overruns and 764 projects were delayed.

“Total original cost of implementa­tion of the 1,902 projects was ₹27,08,030.44 crore, and their anticipate­d completion cost is likely to be ₹32,00,507.55 crore, which reflects overall cost overruns of ₹4,92,477.11 crore (18.19% of original cost),” the ministry’s latest report for February 2024 said.

According to the report, the expenditur­e incurred on these projects till February 2024 is ₹16,76,739 crore, which is 52.39% of the anticipate­d cost of the projects.

However, the number of delayed projects decreases to 568 if the delay is calculated on the basis of the latest schedule of completion, it added.

Further, it said that for 389 projects, neither the year of commission­ing nor the tentative gestation period has been reported.

Out of the 764 delayed projects, 188 have overall delays in the range of 1-12 months, 185 have been delayed for 13-24 months, 275 projects for 25-60 months, and 116 projects have been delayed for more than 60 months.

The average time overrun in these 764 delayed projects is 36.27 months.

Reasons for time overrun, as reported by various project implementi­ng agencies, include delay in land acquisitio­n, obtaining forest and environmen­t clearances, and lack of infrastruc­ture support and linkages.

Newspapers in English

Newspapers from India