Solar rooftop projects moving at snail’s pace

- HT Correspond­ent htraj@htlive.com

JAIPUR: THE CENTRE HAS GIVEN 2,300MW SOLAR ROOFTOP TARGET TO RAJASTHAN BY 2022, WHICH OFFICIALS SAID IS ‘TOO STEEP’

The solar rooftop programme in Rajasthan is progressin­g at a snail’s pace with the total capacity reaching only 52 MW, three years after the state government unveiled a new net metering policy.

Rooftop was expected to receive a fillip after Rajasthan announced net-metering policy in February 2015, under which, an individual could use the power generated and the surplus could be fed into the discom's grid.

The Centre has given a target of 2,300 MW to Rajasthan for solar rooftop by 2022, which according to the officials is “too steep.”

“The staggering pace of the rooftop programme is primarily due to two reasons. First, the domestic consumers are reluctant to invest, since they get their regular power supply (by the discom). Second, the industry and the commercial establishm­ents are not showing any interest after MNRE (ministry of new and renewable energy) discontinu­ed the 30% subsidy,” an official familiar with the matter said.

Under the net metering policy, the government has invited citizens to partner with the company winning the bids and allowing utilisatio­n of their free roof space. Once the project is installed on their rooftops, they are paid a tariff for the energy exported to the grid by the state distributi­on companies (discoms). In October last year, Rajasthan Renewable Energy Corporatio­n Ltd (RRECL) came out with tender for 18 MW of gridconnec­ted rooftop solar projects under the RREC’s rooftop power generation program for 2017-18. However, the interest has been lukewarm.

Rajasthan Electricit­y Regulatory Commission (RERC) issued a tariff order for rooftop solar PV systems covered under RERC net metering regulation­s 2015, where net excess energy (more than 50 units) exported to the grid by the consumers would be paid a tariff of ₹3.93 per unit.

Earlier, the projects being set up by the industry and commercial establishm­ents enjoyed a subsidy of 30% provided by the ministry of new and renewable energy (MNRE). However, the MNRE stopped the subsidy last year.

Admitting the slow pace, RRECL managing director BK Dosi said the government buildings are installing solar rooftop as per their requiremen­t.

 ??  ??