Maha govt officials pulled up for delay

- Naresh Kamath letters@hindustant­imes.com

MUMBAI: We will examine cases, and if we find that officers are responsibl­e for delays, we will pass strictures against them. We will forward cases to the concerned authority, who will take action against guilty officials... GAUTAM CHATTERJEE , MahaRERA chairman

The Maharashtr­a Real Estate Regulatory Authority (MahaRERA) has, so far, cracked the whip on builders, but now it has started taking on Maharashtr­a government authoritie­s for delaying project approvals.

Recently, while hearing a case filed by a group of buyers against M/s Mount Mary Builders and M/s Akshar Space Private Limited over the delay in giving them flats in the Green World project at Airoli, MahaRERA summoned officials from Navi Mumbai Municipal Corporatio­n (NMMC) to explain delays in clearances.

The buyers had contended that they be paid interest as the builders had failed to hand over their flats on time. As per the case, the buyer purchased their flats in 2011 and were to get possession by December 31, 2015.The builders, however, said the delay was beyond their control as the clearance was stuck with the State Environmen­t Impact Assessment Authority and the NMMC.

Officials with NMMC confirmed to the housing regulator in January this year that the owners of the plot had submitted an applicatio­n on August 17, 2011, and were given necessary approvals on June 11, 2013, after a gap of one year and eight months.

Following this, MahaRERA concluded that the date of possession could be extended for reasons beyond the control of the developer, such as like delay in approvals.

In the order, it said: “Considerin­g the disruption in constructi­on work for more than a year and other constraint­s, it is reasonable to extend the date of possession by a year and half to calculate the promoters’ contractua­l liability under section 18 of RERA Act, 2016.” Commenting on summoning NMMC officials, Ashok Mohanani, chairman and managing director of real estate developer Ekta World, said this was a subtle message to government officials. “Many projects are delayed due to the red-tapeism in government department­s. It is time even officials are taken to task for delays,” he said.

Builders have been complainin­g that though developers are being held accountabl­e for project deadlines and being penalised in case of delays, government department­s, who are the approving agencies, are not being held responsibl­e.

Earlier, MahaRERA chairman Gautam Chatterjee had said that guilty officials would be “named and shamed”. “We will examine cases, and if we find that officers are responsibl­e for delays, we will pass strictures against them. We will forward cases to the authority concerned, who will take action under the Right to Services Act,” he said.