Hindustan Times ST (Jaipur)

Govt eases environmen­t rules for coal mines, citing heatwave

Projects previously cleared to operate at 40% capacity may now operate at 50%

- AFP

MUMBAI: India has relaxed environmen­tal compliance rules for coal mines seeking to ramp up production as power outages exacerbate a sweltering heatwave, a government notice showed.

Coal makes up more than two-thirds of India’s energy needs, even as unseasonab­ly hot weather illustrate­s the threat from climate change caused by burning fossil fuels.

Soaring temperatur­es have prompted higher energy demand in recent weeks and left India facing a 25-million-tonne shortfall at a time coal spot prices have skyrockete­d since the start of the year.

In a letter dated May 7 seen by AFP, the environmen­t ministry said it has allowed a “special dispensati­on” to the ministry of coal to relax certain requiremen­ts, such as public consultati­ons, so mines could operate at increased capacities.

The relaxation comes after it received a request from the ministry of coal “stating that there is huge pressure on domestic coal supply in the country and all efforts are being made to meet the demand of coal for all sectors”.

Coal mining projects previously cleared to operate at 40% capacity may now increase capacity to 50% without undertakin­g fresh environmen­t impact studies, the authority said.

The letter coincided with the government launching a new scheme last week to lease abandoned state-owned coal pits to private mining companies, assuring them of fast-track environmen­t approvals.

“The ministry of environmen­t and forests understand­s that they need to cut out the red tape,” coal ministry official Anil Kumar Jain said at the launch event.

The government hopes to woo private mining giants such as Vedanta and Adani to revive more than 100 dormant coal mines previously deemed too expensive to operate, using new technology and fresh capital.

India needs a billion tonnes of coal annually to meet its current domestic demand.

Most of its needs are met by domestic producers, with a record 777 million tonnes mined in FY22. The shortfall is imported from countries such as Indonesia, Australia and South Africa.

The government says it plans to increase domestic coal production to 1.2 billion tonnes in the next two years to support a post-pandemic economic recovery. Despite a commitment to increase its renewable energy capacity to 175 gigawatts by 2022 and 500 gigawatts by 2030, Coal and mines minister Pralhad Joshi said India’s coal needs are set to double by 2040.

A renewed focus on accelerati­ng coal production risks India missing Prime Minister Narendra Modi’s COP26 commitment to meet 50% of energy demand through renewable energy by 2030, according to experts.

 ?? ANI ?? The higher energy demand in recent weeks has left India facing a 25-million-tonne shortfall at a time coal spot prices have skyrockete­d.
ANI The higher energy demand in recent weeks has left India facing a 25-million-tonne shortfall at a time coal spot prices have skyrockete­d.