MUTP3FORCR,WR: Onslowtrac­k since‘16

No clarity on funds; project, aimed at improving connectivi­ty in Mumbai Metropolit­an Region, is stuck; World Bank to give decision by December

- Aroosa Ahmed

MUMBAI : Almost two years after getting Cabinet nod, the Mumbai Urban Transport Project (MUTP) 3, a project aimed at boosting rail connectivi­ty in the Mumbai Metropolit­an Region (MMR), is stuck for want of funds.

Of the estimated cost of ₹10,948crore, ₹6,000 crore has been sought from the World Bank. According to the Mumbai Rail Vikas Corporatio­n (MRVC), the nodal agency responsibl­e for executing major infrastruc­ture projects related to suburban railways, the World Bank is studying and reviewing the projects. “Talks with World Bank over the funding are going on. We are expecting a final decision by December,” said RS Khurana, chairman and managing director, MRVC.

Railway officials feel MUTP-3 may miss its 2022 deadline, despite major infrastruc­ture projects being expedited. “After we get an official nod from the World Bank, we will take a minimum of nine months to finish tendering, issue work orders and complete other formalitie­s. Although a few parts of the project might begin, the main work is likely to start only by the end of 2019. Meeting the deadline seems difficult,” said a senior MRVC official.

MRVC is yet to start land acquisitio­n for the project, which includes quadruplin­g of Virardahan­u Road section (63km), suburban corridor between Panvel and Karjat (28km), elevated corridor link between Airoli and Kalwa (3km), among others. The MRVC has expedited the work on the Panvel-vasai-virar corridor and included it in under MUTP-3. All these corridors will provide connectivi­ty to areas witnessing substantia­l real estate developmen­t around the new internatio­nal airport and is expected to decongest the city. However, without rail connectivi­ty, it will be difficult to populate the many smart cities that are coming up in these areas.

While MUTP-3 is delayed, the ₹55,000-crore next phase, MUTP-3A, has been sent to the railway board for nod in June. The project will go to Niti Aayog, after the Union cabinet gives final nod. The deadline is 2023.

Thane

STATUS OF PROCUREMEN­T OF NEW LOCALS FOR

MUTP-3 Research Designs and Standards Organisati­on (RDSO), Lucknow, has already frozen designs of AC locals for Mumbai.

Kalwa

Airoli

Mankhurd

Nerul

Wadala Rd

Vashi New suburban corridor link between

Airoli Kalwa (elevated) on Central Railway

Belapur

Kalyan

Panvel

Badlapur

New suburban corridor between Panvel-karjat on Central Railway (double line)

 ??  ??