Hindustan Times ST (Mumbai)

74% tunnelling for Metro-3 completed

- HT Correspond­ent

MUMBAI: The Mumbai Metro Rail Corporatio­n (MMRC), which is executing the fully-undergroun­d Metro-3 line (Colaba-bandraseep­z), has completed 74% of the tunnelling work for the corridor. As of December 26, MMRC has completed 40-km tunnelling of the total 54.5-km twin-tunnel line. SK Gupta, director (projects), MMRC tweeted: “a very important milestone indeed achieved by consistent efforts in difficult conditions.”

MMRC has also completed 24 of the 32 tunnel breakthrou­ghs. In a newly-released timeline for next year, the corporatio­n is looking at completing all the tunnelling in the city by September 2020.

A spokespers­on from MMRC said, “In 2020, we are looking forward to major landmarks. We are expecting to complete 70% of the civil works in 2020. The first rolling stock is expected by December 2020 and the tracklayin­g work for the main line will also start next year.”

Each of the Metro trains will be 177.2 metre long, with a capacity of carrying 3,000 passengers.

While the first phase was initially set to be operationa­l from December 2020, MMRC is looking at making the line partly operationa­l (Aarey-bandrakurl­a Complex) by June 2021.

MMRC will also be inviting bids for the operation and maintenanc­e of the corridor in February and is looking at awarding tenders for two of the three rehab buildings in Girgaum-kalbadevi areas.

The ₹23,136-crore project is partially being funded by Japan Internatio­nal Co-operation Agency (JICA) through a loan of ₹13,235 crore.

The third tranche of the loan is expected by March 2020.

Newspapers in English

Newspapers from India