Coastal rd work: 1km of tunnelling work completed

- Eeshanpriy­a MS

MUMBAI: India’s largest tunnelbori­ng machine (TBM) — Mavla — that is being used for tunnelling work for Brihanmumb­ai Municipal Corporatio­n’s (BMC) ambitious coastal road project, has completed one-kilometre work on Saturday, at 11.40pm.

The tunnel boring work began in January 2021.

Imported from China in May 2020 and assembled here, it is the country’s largest TBM, with a diameter of 12.9 metres.

The 10.58km coastal road that will connect Nariman Point to Bandra Worli Sea Link has twin tunnels of 2.07km, connecting Girgaum Chowpatty to Malabar Hill.

Each undergroun­d tunnel will have three lanes at a depth of 70 meters.

Work is ongoing on the south-bound arm of the tunnel, where 1km of boring work was completed on Saturday.

The remaining kilometre of this tunnel will be completed by January.

As per BMC’S original plan, the tunnelling work on both tunnels is expected to be completed within 18 months. The civic body lost three months of time after tunnelling work started, during city-wide restrictio­ns since March 2021, amid the second wave of Covid-19 pandemic.

BMC has presently completed 40% of the work on the coastal road project, and 102 hectares of reclamatio­n work is complete.

According to BMC’S original timeline, by December 2021, 55% of the work should be complete; and by December 2022, 85% of the work should be complete.

Vijay Nighot, chief engineer of the coastal road department said, “The civic body lost a total of six months due to restrictio­ns imposed because of covid-19. The deadline for completion of the project is December 2023.”

 ??  ?? The tunnel-boring work began in January 2021.
The tunnel-boring work began in January 2021.