Hindustan Times ST (Mumbai)

Coastal road cost rose 405%, CAG asks why

- Mehul R Thakkar

MUMBAI: The Comptrolle­r and Auditor General of India (CAG), the country’s apex public expenditur­e auditing body, has questioned the Brihanmumb­ai Municipal Corporatio­n (BMC) over a sharp increase in constructi­on cost of the Mumbai Coastal Road Project (MCRP) from ₹252 crore per kilometre in 2011 to ₹1274 crore in 2018, a 405% rise. It has also raised questions over separate spends amounting to ₹200 crore in an inspection report between April 2016 and March 2020. The total expenditur­e in the latter part amounted to ₹2100 crore, of which ₹200 crore has been called into question.

The report was submitted to the BMC in July 2021, but is not made public yet. HT accessed a copy.

In 2010, a 35-km coastal road was planned between Nariman Point in south Mumbai and Kandivli in the north of the city for smoother traffic movement. However, the project never took off for eight years. In October 2018, the BMC began constructi­ng the 9-km-long first phase between Princess Street Flyover near Marine Drive and Worli which will take motorists up to Versova in suburban Mumbai via the Worli-bandra sea link and the under-constructi­on Bandra-versova sea link.

Though constructi­on began in October 2018, expenses piled up for nearly a decade owing to studies and the tendering process executed with the help of third-party consultant­s. The CAG scrutinise­d the civic body’s coastal road department’s expenditur­e between April 2016 and March 2020.

The primary question is that of cost escalation. The CAG pointed out that the Coastal Road cost ₹252 crore per km in 2011, ₹304 crore in 2016, ₹686 crore in 2018 and finally went up to ₹1,274 per kilometre. The report says, “It is seen that the cost of work worked out for coastal road ranged between ₹252 crore and ₹1,274 crore. Huge variation in the costs needs justificat­ion.”

The BMC in its response has submitted the justificat­ion for which the progress is awaited, said the report.

According to BMC officials, they corporatio­n has been complying with the queries from the CAG from time to time. A senior official from the engineerin­g department of the coastal road said, “There were several queries raised by the CAG as part of their inspection report. We have, from time to time, satisfacto­rily replied to the queries of the CAG. There is nothing more to be read in the same. We have been complying with the CAG’S requests.”

The report also questioned financial dealings of around ₹200 crore ranging from fine collection, non-recovery of penalties, loss of income from interest, excess/undue payment made to contractor­s and consultant­s.

One such expenditur­e was of ₹8.57 crore made by the BMC towards consultanc­y work for the coastal road. In another instance, the CAG questioned a payment of ₹142 crore to contractor­s, despite there being a stay by the Bombay high court between July 2019 and December

2019. In its report, the CAG stated, “It is seen that the work was totally stopped during July 16, 2019 to January 1, 2020 and was again commenced on January 2, 2020. Thus, the contractor is not entitled for any payment for this period. However, scrutiny of bills paid to the contractor revealed the payments made ₹73.92 crore + ₹68.27 crore made which includes the payment for the period 16th July 2019 to 1st January 2020.” It added, “MCGM (BMC) was asked to furnish justificat­ion for the same. In reply, MCGM stated that abiding by the court order the constructi­on/physical work was not carried out. Only the work related to submission­s relevant to preliminar­ies and design were continued during the site work stoppage period and the payment for design submission­s was released. However, the reply is not acceptable as the coastal road work also includes design works which should have stopped as per the Bombay High court order.”

In another instance, the CAG stated that undue benefit was given to the contractor due to non-levying/withholdin­g of penalty of ₹27.99 crore. The report said, “It could be seen that there is no uniformity in levy and recovery of penalty. It could be construed that the tender conditions envisaged were not proper because huge penalty charges (hypothetic­al) were enlisted, levied, but not recovered.”

Eight queries were raised in total by the CAG. BMC says it replied to some of the CAG’S queries, while some are under process. In some cases, a reply is awaited and in some, the CAG is not satisfied.

 ?? HT PHOTO ?? In October 2018, the BMC began building the 9-km-long, first phase of the Coastal road project, between Princess Street Flyover and Worli.
HT PHOTO In October 2018, the BMC began building the 9-km-long, first phase of the Coastal road project, between Princess Street Flyover and Worli.

Newspapers in English

Newspapers from India