Hindustan Times ST (Mumbai)

CAG questions BMC on traffic study

- Mehul R Thakkar SATISH BATE/HT FILE

MUMBAI: The Comptrolle­r and Auditor General of India (CAG), the country’s apex public expenditur­e auditing body, has questioned the Brihanmumb­ai Municipal Corporatio­n (BMC) over its traffic estimates for the ambitious Mumbai Coastal Road Project (MCRP) and stated in its report that scrutiny of records revealed that a “detailed and proper analysis of traffic for Mumbai Coastal Road Project was not done”.

The CAG submitted its report to the BMC in July 2021, a copy of which was accessed by HT. The CAG asked the BMC to clarify whether Metro services (existing as well as under constructi­on) were considered while preparing its traffic study. It also pulled up the BMC stating that some of its estimation­s “appeared to be imaginary”.

“The CAG had raised certain points in regards to the traffic study of Coastal Road project. However, we had satisfacto­rily responded to them. We are complying on all the points that have been raised by the CAG,” said a senior BMC official from engineerin­g department of Coastal Road who did not wish to be named.

A brief background

In 2009, the Mumbai Metropolit­an Region Developmen­t Authority (MMRDA) conducted a Comprehens­ive Transporta­tion Study (CTS) that first mooted the need for a coastal road. In 2011, a Joint Technical Committee, under the chairmansh­ip of the Municipal Commission­er of the BMC, recommende­d a 35.60 km-long Coastal Road consisting of roads based on reclamatio­n, bridges, elevated roads and tunnels on the western side of

Mumbai. This was meant to run from Kandivli to Nariman Point. The BMC commission­ed a traffic study of the Coastal Road in 2015 and started work on a 9.98 km stretch from Princess Street flyover to Worli — referred to as the southern part of the Coastal Road — in October 2018.

Pain points

According to the CAG report, the BMC did not take proper considerat­ion of the cost benefit ratio, average daily traffic report, car ownership and population growth and account for the Metro corridors in the city.

“It was observed that there are works related to 15 Metro lines spanning a network of 356.972 km with 226 stations in pipeline. Out of which line-1 (11.07 km) was made operationa­l in 2014. A total of 88.88 km of Metro network falls under the southern part of the city. It was estimated (in January 2019) that there will be a daily ridership of 4.50 lakh with an annual ridership of 12.60 crore. It was observed that MSRDC and MMRDA had considered the Metro network and its ridership while computing the traffic on the northern part of the Coastal Road,” it said.

“However, there is no specific considerat­ion and analysis on the Metro network (southern part) as such the actual traffic which usually prefers local train services, BEST to private vehicles would opt for Metro services only as an alternativ­e to cars/taxis,” the report stated. The CAG acknowledg­ed that the Coastal Road would be used by fast-moving four wheelers like cars and taxis, but two and three-wheelers, which account for a chunk of the traffic in this southern section would not be able to use the Coastal Road. “Two and three wheelers account for 20% of the actual number of cars that are not allowed on southern part of this road. This indicated that the entire project was designed mainly for fasting moving vehicles as half of the traffic would be using Western Express Highway and Freeways,” it noted.

The CAG report called into question the BMC’S estimates. “It was observed that in main traffic report, the car ownership per 1000 population was pegged at 139 (2011), 204 (2021), and 266 (2031) and thereafter it would stabilise at 180 car ownerships per 1000 population. Further, car growth was huge during 2014-24 and 2024-34. But at the same time for correspond­ing years, the actual population was estimated at an average of 2% growth. These figures appear to be imaginary and the department was asked to justify the figures.”

BMC responses

HT had previously reported that the CAG report also questioned the BMC over a sharp increase in constructi­on cost from ₹252 crore per kilometre in 2011 to ₹1274 crore in 2018, a 405% rise. It also raised questions over separate spends amounting to ₹200 crore in an inspection report between April 2016 and March 2020.

In a press conference on Tuesday, Bharatiya Janata Party (BJP) leader Ashish Shelar said: “The CAG report has questioned the BMC on several issues ranging from over Rs 200 crore expenditur­e towards clearing bills of contractor­s and consultant­s to the traffic study and project report prepared by the BMC for the project. The CAG has also questioned BMC as to why they have not submitted a plan on utilisatio­n of green space that is being reclaimed to the union environmen­t ministry? This questions the BMC’S intention to keep green space intact nearby coastal road.”

Responding to the allegation­s about irregulari­ties, the BMC issued a statement on Tuesday.

“No fraud or irregulari­ties have been committed in the Coastal Road Project undertaken by the BMC. The allegation­s circulatin­g in this regard are baseless and incorrect. BMC strongly denies all the allegation­s. The first allegation is no traffic analysis done and traffic study is flawed. But the draft report was published on BMC website in 2015. The DPR was finalised by M/s. Stup and E.Y. and has been peer reviewed by M/s. Frishmann Prabhu. The traffic analysis was done in the said DPR. This was also submitted to Maharashtr­a Coast Zone Management Authority (MCZMA) and Union environmen­t ministry.”

On the over Rs 200 crore payment to contractor­s and consultant­s, the BMC said: “All payments due to the contractor­s are done by following due procedure as per recommenda­tion of Project Management Consultant­s. As such no payment has been done to the contractor­s without doing the work.”

 ?? ?? Worli fishermen protest the Coastal Road project at Worli, in October.
Worli fishermen protest the Coastal Road project at Worli, in October.

Newspapers in English

Newspapers from India