Hindustan Times ST (Mumbai)

14 homebuyers awarded 20% refund for delay in possession

-

Kanchan Chaudhari

MUMBAI: In a big relief for 14 buyers who purchased flats in Hubtown Sunstone at Bandra east, the developer has been directed to refund 20% of the flat price on account of a three-andhalf-year delay in delivery of flats.

The National Consumer Disputes Redressal Commission (NCDRC) recently allowed homebuyers’ complaints about compensati­on due to the delay in handing over possession.

The NCDRC directed Sunstone Developers to pay the 14 homebuyers interest at the rate of 9% per annum on the amount paid by them for the period of delay -- from March 31, 2014, when the possession of ready flats was supposed to be delivered to September 2, 2017, when the developer offered possession of ready flats.

NCDRC bench of justice RK

Agrawal and Dr SM Kantikar on May 4 directed the developer to pay an additional amount of ₹25,000 to each of the complainan­ts towards litigation costs.

One of the complainan­ts, Nagesh Utekar, had agreed to purchase a flat admeasurin­g 690 square feet of carpet area on the sixth floor of the proposed building for total considerat­ion of ₹1.96 crore.

The agreement between the parties was executed on March 31, 2012, and under the agreement, the developer had agreed to deliver ready flats by March 31, 2014.

In 2017, Utekar (and 13 others) moved the NCDRC seeking compensati­on as the developer failed to deliver the flat although he had paid around 80% of the total considerat­ion.

The developer contested the complaint, claiming that the project got delayed because of reasons beyond their control, as the change in Developmen­t Control Regulation­s for the city and SRA policy affected the generation of the Floor Space Index.

Besides, the developer also cited the non-availabili­ty of cement, steel and other constructi­on materials and contended that from time-to-time flat purchasers were duly informed of the extended dates of delivery and a deficiency in service.

The developer’s counsel claimed that since the complainan­ts had delayed payment of the balance 20% considerat­ion, they were liable to pay interest at the rate of 24% per annum, as contemplat­ed under the agreement.

The NCDRC, however, refused to accept the developer’s contention­s, after noticing that the change in DCR and SRA policy came in July 2014 -- much after the agreed date for delivery of possession, March 31, 2014.

As regards the plea of shortage of constructi­on materials, the commission said there was cogent evidence to support the claim.

“Even otherwise,” the NCDRC said, “it is the duty and responsibi­lity of the developer to manage the raw/constructi­on material and the complainan­ts (flat purchasers) cannot be made a victim for the same.”

It is the duty and responsibi­lity of the developer to manage raw/constructi­on material. Buyer cannot be made a victim NCDRC BENCH

Newspapers in English

Newspapers from India