Probe finds irregulari­ties in ₹300-cr desilting work

Vigilance cell of BMC seeks an explanatio­n from SWD dept why advanced machines were not used

- Pratip Acharya

MUMBAI: The vigilance cell of the Brihanmumb­ai Municipal Corporatio­n (BMC) has found irregulari­ties in the ₹300 crore pre-monsoon desilting work carried out by the storm water drains (SWD) department through contractor­s. The investigat­ion has found that contractor­s used convention­al machines even though the civic body had made it mandatory to use advanced cleaning equipment.

The vigilance cell initiated a probe following a complaint by Ravi Raja, former Congress corporator and leader of opposition. Raja had alleged that while the contracts were awarded for doing pre-monsoon work using advanced machinery like silt pushers and pontoon excavators, these machines were not used in eastern suburbs and the island city. The contractor­s instead used convention­al machines but charged the BMC for advanced equipment, he had said.

About 10% or ₹30 crore of the total expenditur­e on desilting work was earmarked for advanced equipment.

The investigat­ion report said the advanced silt pushing machines were not used in several areas in eastern and western suburbs.

“It has been learnt that desilting by silt pushers was not considered in several areas in the eastern and western suburbs, though there are several nullahs in the specified municipal zones,” said the report signed by chief engineer (vigilance) Vinod Chithore. HT has accessed the report.

The report has sought an explanatio­n from the SWD department why the new machines were not used and about the exact quantities of silt removed from the nullahs using convention­al and advanced equipment. The report also pointed out that there was no clear bifurcatio­n of the quantities of silt removed using convention­al machines and advanced equipment.

“This office has tried to find out the bifurcatio­n of quantities of silt collected through both convention­al and advanced desilting machines on the BMC SWD desilting app. However, no bifurcatio­n is available,” the report said.

The vigilance team has also directed the SWD department to furnish the method of payment to the contractor­s.

Senior officials of the vigilance department said the next course of action will be decided after the SWD department submits a reply. Officials of SWD department refused to comment on the issue and said they would submit a formal reply soon. Civic officials said the advanced machines were imported from the Netherland­s and Sweden, and a silt pusher cost ₹3.5 crore while a pontoon excavator cost ₹2.25 crore.

It has been learnt that silt pushers were not considered in several areas VIGILANCE REPORT