CURRENTLY, THE ELECTRICIT­Y DEMAND IS 500 MW PER DAY IN THE CITY AND IT IS EXPECTED TO INCREASE TO 1,500 MW BY 2031

GREATER NOIDA The Greater Noida authority on Tuesday sanctioned ₹1,000 crore to upgrade and enhance the existing infrastruc­ture in the city to supply electricit­y as per the expected future demands in the newly developed residentia­l and industrial clusters.the authority plans to set up as many as five additional power sub-stations to meet the increasing power demand.

The move comes after officials noted an increase in the occupancy level in residentia­l areas in the city and an increase in the local population in view of the ongoing Noida Internatio­nal Airport work. Currently Greater Noida’s population is around 800,000 and it is expected to increase up to 2,500,000 by 2031, said officials.

Currently the electricit­y demand is 500 megawatt per day in Greater Noida and it is expected to increase three times of what it is now, stated an official estimate. To meet the future demand, the authority has decided to spend ₹1,000 crore on setting up 5 new power substation­s in different areas.

“If we start work on these power sub-stations now, then only the city will be able to get required electricit­y supply in the time to come. We have sanctioned ₹1,000 crore for 5 new sub-stations,” said Deep Chand additional chief executive officer of the Greater Noida authority.

The Greater Noida authority’s top officials also met with officials of Noida Power Corporatio­n Limited(ncpl) and planned to set up sub-stations.

Currently, Greater Noida has 16,000 consumers in urban areas and 65,000 consumers in rural areas. With the increase in occupancy of vacant flats, the demand for the power supply is bound to go up.

“With the rise in population, the pressure on sewer lines, drainage network and other infrastruc­ture is also expected to rise. So will the demand of electricit­y. If we need to maintain the quality of civic amenities, then we need to increase the supply of electricit­y,” said Chand.

According to the authority, it has planned to set up one 400 KV power sub-station in village Amarpur, two 220KV stations, one each in Jalpura and Sector Knowledge Park-5, two power sub-stations of 132KV each in Sector Ecotech 8 and one in Sector Ecotech 10.

The Greater Noida authority will enhance the capacity of 220KV power sub-station in Sector 123 to 400KV, said officials.

Currently the city depends on a 132KV sub-station located in Surajpur and 220 KV sub-station in RC Greens, said officials.

“We are working well in advance to provide uninterrup­ted power supply to our consumers anticipati­ng an increase in demand,” said S Ganguli vicepresid­ent of NPCL.

 ?? HT ARCHIVE ?? The authority has planned to set up five new power sub-stations in different areas.
HT ARCHIVE The authority has planned to set up five new power sub-stations in different areas.

Newspapers in English

Newspapers from India