Agra Metro expansion progresses with four tunnel boring machines

- HT Correspond­ent letters@htlive.com SOURCED

AGRA : After the priority corridor became operationa­l and the metro commenced its services, attention has shifted to expanding the Agra Metro Rail Project. The Uttar Pradesh Metro Rail Corporatio­n is now advancing with four tunnel boring machines in the remaining undergroun­d section of the first corridor of the Agra Metro rail project.

Tunnel boring machines (TBMs) 3 and 4 have finished the up and down tunnels between the RBS ramp area and RBS College Metro Station. Meanwhile, TBMs 1 and 2 are constructi­ng a tunnel from Agra College towards Mankameshw­ar Temple Metro Station.

Sushil Kumar, managing director of UP Metro, said, “After the metro services commenced in the Priority Corridor ahead of schedule, the UP Metro team is working with full dedication to provide metro services to the city residents in the remaining section soon.

Currently, tunnel constructi­on in the remaining part of the first corridor is progressin­g with four TBMs. In this section, two TBMs (TBM 3 and TBM 4) were launched in the up-anddown lines from the launching shaft in the RBS ramp area towards RBS College Metro Station.

Both TBMs have achieved their first breakthrou­gh at RBS College Metro Station.

Soon, these TBMs will be launched towards Raja ki Mandi Metro Station. TBMs 3 and 4 will construct the tunnel from the ramp area to Agra College Metro Station.

Simultaneo­usly, TBMs 1 and 2 have been launched for tunnel constructi­on in the direction from Agra College to Mankamshwa­r Metro Station.

 ?? ??
 ?? ?? Agra Metro expansion advances
Agra Metro expansion advances