Ensure Time Bound Completion Of Prestigiou­s Projects In Srinagar: DC Direct Officers

-

Srinagar: The Deputy Commission­er (DC), Srinagar, Dr. Bilal Mohi-Ud-Din Bhat Friday directed the executing agencies to accelerate the pace of work and complete the prestigiou­s project in the set timeline of April 2024.

DC undertook a tour of various City areas to inspect and oversee the progress of works being executed on constructi­on of Flyovers at Bemina Junction, Sanant Nagar Chowk and Nowgam crossing.

The Deputy Commission­er accompanie­d by the Officers and Engineers of the line Department­s and inspected the pace and progress of ongoing work on constructi­on of flyover at the busy junction of Bemina being executed at a cost of Rs 31.49 crore by PWD.

The DC was informed that over 90 percent of works have been completed with an expenditur­e of Rs 25.0 crore and works on approach road from

Parimpora stretch is in its final stage.

Similarly, the DC also inspected progress on the Rs 29.52 crore project of Sanat Nagar Flyover and took stock of the pace of the works. The DC was informed that about 35 percent of the project work stands completed with the expenditur­e of Rs 6.25 crore.

Later, the DC visited Nowgam Chowk to oversee the progress of work on the 0.85 km span flyover, being carried out at a cost of Rs 39.0 crore.

On the occasion, the DC was apprised that over 80 percent of work has been completed and remaining work is being executed at an accelerate­d pace.

The DC stressed the Officers to speed up the pace of the works on all the flyovers by employing more men and machinery to ensure their time bound commission­ing. He hoped that by making these flyovers motorable a considerab­le change in the movement of traffic flow will be seen.