Millennium Post

331 infrastruc­ture projects see cost overrun of ₹1.72 lakh crore: Report

-

NEW DELHI: As many as 331 infrastruc­ture projects, each worth Rs 150 crore or above, have seen a cost overrun of Rs 1.72 lakh crore because of various reasons including delays, according to a government report.

Ministry of Statistics and Programme Implementa­tion monitors infrastruc­ture projects worth Rs 150 and above.

The total original cost of implementi­ng 1,257 projects was Rs 15,76,903.56 crore, and their anticipate­d completion cost is likely to be Rs 17,49,274.62 crore, cost overrun of Rs 1,72,371.06 crore (10.93 percent of the original), the ministry’s flash report for July this year has stated.

The expenditur­e incurred on these projects till July is Rs 6,80,016.96 crore, which is 38.87 percent of the total anticipate­d cost.

The 1,257 projects in question include 331 that reported cost overrun and 274-time escalation.

“Out of a total of 1,257 projects, two projects have reported completion, and ten new projects have been initiated on the monitor of this ministry during the current month (July).

Of these, 11 projects are ahead of schedule, 304 are on track and 274 are delayed, 331 projects are showing cost overrun and 92 projects are showing both time and cost overrun concerning original implementa­tion schedules.”

However, the report said that the number of delayed projects decreases to 215 if the delay is calculated with reference to latest revised schedules of completion.

The report also highlights that for 668 projects, the original/anticipate­d commission­ing dates were not reported by the authoritie­s concerned.

It further said that out of 274 delayed projects, 47 have an overall delay in the range of 1 to 12 months, 59 have a delay in the range of 13 to 24 months, 101 have a delay in the range of 25 to 60 months and 67 have a delay of 61 months and above.

Of the 1,257 projects, 372 are mega projects worth Rs 1,000 crore and above.

The total original cost of implementa­tion of these 372 projects was Rs 12,17,096.27 crore, and their anticipate­d completion cost is likely to be Rs 13,60,528.92 crore, which reflects overall cost overruns of Rs 1,43,432.65 crore (11.78 per cent of the original cost).

The expenditur­e incurred on these mega projects till July was Rs 5,70,750.91 crore, which is 41.95 per cent of the anticipate­d cost of the projects.

Out of the 372 mega projects, 130 have cost overruns with respect to original cost and the number of such projects decreased to 103 when cost overrun is calculated by revised cost.

 ??  ??

Newspapers in English

Newspapers from India