Millennium Post

Signature Bridge across Yamuna to be completed by Oct, HC told

Courts ask authoritie­s to file a status report, fixes matter for November 14

- ROUSHAN ALI

NEW DELHI: The Delhi High Court was informed on Friday that the long-delayed Signature Bridge across the Yamuna river would be completed by October after which trials would be conducted. A bench consisting of Chief Justice Rajendra Menon and Justice VK Rao asked the authoritie­s to file a status report while fixing the matter for November 14.

“List the matter in the second week of November to enable the respondent­s (authoritie­s) to complete the project and do the trial and file a report,” the bench said.

The court was informed by the counsel for the Public Works Department (PWD) that the project will be completed by October and trial run will be conducted thereafter. Meanwhile, Delhi Deputy Chief Minister Manish Sisodia on Thursday inspected the work on the much-awaited Signature Bridge on the Yamuna river and promised to pay weekly visits at the site to speed up its completion. Constructi­on of the bridge has been delayed, but once completed it will save travel time of millions of northeast Delhi residents and serve as a “crown” of Delhi tourism, he said.

The court had earlier frowned upon two city government department­s for “quibbling over” the amount to be paid for the constructi­on of the “long overdue” Signature Bridge. “A sum of Rs 1,380.1 crore, of the said amount of Rs 1,518.37 crore, has been released. The balance of Rs 1,38.27 crore is to be paid after funds are released by the Delhi government,” said the PWD counsel.

On July 12, Delhi government had approved the final revised estimate of Rs 1518.37 crore for the con- struction of Signature Bridge on Yamuna river at Wazirabad. Conceptual­ised in 2004, the project –India's first asymmetric­al cable-stayed bridge –was approved by the Sheila Dikshitled Cabinet in 2007. Constant delays, however, escalated the cost. It was initially estimated to cost Rs 459 crore, which rose to Rs 1,131 crore in 2010.

The Signature Bridge, when completed, is expected to share the burden of vehicular traffic which is being borne by the Wazirabad bridge, which itself, according to the PWD, requires “structural rehabilita­tion and strengthen­ing”.

According to the government, the bridge had obtained environmen­tal clearance in 2011 and was set to be completed by December 2013. The date of completing the project was pushed to June 2016 and then to July 2017, which had been further shifted to December 2017. It had directed the chairperso­n of the Delhi Tour- ism and Transport Developmen­t Corporatio­n (DTTDC) and the chief of engineerin­g of the PWD to physically inspect the bridge and the alternativ­es provided to the citizens to satisfy themselves about the constructi­on. The bridge will connect Delhi with many industrial areas of Uttar Pradesh, like the Tronica city in Ghaziabad.

The court was earlier informed by the PWD that it had already paid Rs 1,344 crore for the project as against the initially agreed cost of Rs 544 crore, and now the DTTDC was asking for Rs 200 crore more. The DTTDC, on the other hand, had told the court that the cost of the project has escalated. The court was hearing a PIL by advocate Pratibha Chopra, who pointed to the inordinate delay in the project and alleged that the constructi­on of the bridge had missed several deadlines since 2011.

 ??  ??

Newspapers in English

Newspapers from India