401 infra projects show cost overruns of `4.06 lakh crore

-

NEW DELHI: As many as 401 infrastruc­ture projects, each worth Rs 150 crore or more, have been hit by cost overruns of over Rs 4.06 lakh crore owing to delays and other reasons, according to a report.

The Ministry of Statistics and Programme Implementa­tion monitors infrastruc­ture projects worth Rs 150 crore and above.

Of the 1,701 such projects, 401 projects reported cost overruns and 583 projects time escalation.

“Total original cost of implementa­tion of the 1701 projects was Rs 20,65,739.00 crore and their anticipate­d completion cost is likely to be Rs 24,71,954.78 crore, which reflects overall cost overruns of Rs 4,06,215.78 crore (19.66 per cent of original cost),” the ministry’s latest report for December 2019 said.

The expenditur­e incurred on these projects till December 2019 was Rs 10,89,178.11 crore, which is 44.06 per cent of the anticipate­d cost of the projects.

However, it said the number of delayed projects decreases to 483 if delay is calculated on the basis of latest schedule of completion.

Further, it said that for 748 projects neither the year of commission­ing nor the tentative gestation period has been reported.

Out of 583 delayed projects, 183 have overall delay in the range of 1 to 12 months, 129 in the range of 13 to 24 months, 146 reflect delay in the range of 25 to 60 months and 125 projects show delay of 61 months and above.

The average time overrun in these 583 delayed projects is 39.40 months. The brief reasons for time overruns, as reported by various project implementi­ng agencies, are delays in land acquisitio­n, forest clearance and supply of equipment.

 ??  ??