CPWD asked to probe ‘ cutting’ of 100 trees on Barapullah corridor

- AGE CORRESPOND­ENT

The National Green Tribunal ( NGT) has directed the Central Public Works Department ( CPWD) to look into the alleged cutting of 100 trees in a park at the Tyagraj Nagar market here during the constructi­on of the second phase of the Barapullah elevated corridor. A bench headed by NGT chairperso­n Justice Adarsh Kumar Goel asked the authoritie­s to look into the allegation­s raised in a petition and take action as per law.

“The allegation­s will require to be looked into and action taken as per law. We direct that the matter be looked into by CPWD and PWD, Delhi. They may look into the alleged violations of the Forest Act on account of cutting of trees and the Environmen­t ( Protection) Act, 1986 on account of destroying the park and take action within one

month,” the bench, also comprising Justice Jawad Rahim, said.

The tribunal made it clear that in case of noncomplia­nce of the order, coercive measures as provided under the National Green Tribunal Act, 2010, may have to be taken, including imposition of cost and direction of prosecutio­n

of the persons responsibl­e, including the head of the department­s concerned. The direction came while the bench was hearing a plea filed by Tyagraj Nagar Market ( Prem Nagar), which alleged that due to the constructi­on of the ramp of the Barapullah elevated corridor- II, the park in the Tyagraj Nagar market was damaged. The constructi­on of an office had led to the cutting of 100 trees and loss of water bodies, the petition alleged.

After missing a number of deadlines, the second phase of the Barapullah elevated corridor between Sarai Kale Khan and INA Market at Aurobindo Marg was inaugurate­d by Delhi chief minister Arvind Kejriwal on July 28. The work on the second phase of the flyover, sanctioned in 2012 and started a year later, was initially slated to be completed by 2015. The deadline was first extended to September 2017, then to December 2017 and then to March 2018. It also missed its June 2018 deadline. The flyover will not only connect east and south Delhi, but also help commuters from east Delhi, Ghaziabad and Noida to reach the AIIMS and Safdarjung hospitals in lesser time.