The Free Press Journal

Only 45% of BKC flyover completed

- SAGAR PILLAI Mumbai

Three years after the Bandra Kurla Complex-Chunabhatt­i flyover project was awarded by Mumbai Metropolit­an Region Developmen­t Authority, the blackliste­d contractor J Kumar has only managed to complete 45 per cent of the work. The flyover project was awarded in August 2014 and had a three-year deadline. However, officials cited that acquiring permission­s and the rehabilati­on of slum dwellers led to the delay in project

The project was stalled due to lack of permission­s from various government agencies since it will jump the Mithi River stream and the railway tracks. The 1.6 km long flyover will start from G Block of BKC and will snake through Mithi River, LBS Marg, railway tracks of Central Rline and Harbour line, Somaiya Ground and will finally connect the Eastern Express Highway near Everad Nagar.

A senior MMRDA official said that it was a three year contract originally which got further extended as the permission­s from Somaiya trust arrived late. "There were 70 slums that were supposed to be cleared in order to connect the flyover which took some more time. Moreover, it was a prolonged process to acquire permission­s from Somaiya trust since the flyover will be crossing the famous somaiya ground. The 70 families, Project Affected People, have been rehabilita­ted successful­ly," he added.

The official added that the deadline has been extended till December 2018. The connector will involve the constructi­on of 260 metre long bridge on the Mithi River for which only the pillars have been erected so far. In adddition to this, a rail over bridge over the two railway lines will also be constructe­d.

Another official revealed that the railway authoritie­s were unhappy with the height of the bridge according to the project design. He explained, "The authoritie­s had first agreed to give permission to the flyover. However, they suddenly revoked their decision and asked to make some technical changes. They wanted to increase the height of the flyover which we had agreed to after conducting a meeting with them. Such permission led to more delay in the project."

The official added that currently a final approval is pending from the railway authoritie­s. He said, "The approval of General Arrangemen­t Drawing (GAD) is yet to be received after which the flyover will be completed."

The 1.6-km-long connector, which is expected to cut travel time by 30 minutes and distance by 3 km, will decrease traffic congestion in Sion and Dharavi areas.

 ??  ??