Constructi­on work of MTHL to begin from next month

- STAFF REPORTER

The constructi­on work of the ambitious Mumbai Trans Harbour Link (MTHL) is set to begin in March with the completion of the on-going geological survey by the planning authority.

The survey which is being conducted by Mumbai Metropolit­an Region Developmen­t Authority (MMRDA) began from January 15 onwards. This was necessary in order to assess the soil before the constructi­on work begins for this project work.

The survey is being conducted by a team of four contractor­s who have been finalized for MTHL project.

“The contractor­s have used boats for the survey in order to venture into the sea to conduct the soil testing work. Currently, the land on which the piers are set to be erected is being assessed, to study if the venture is feasible. The soil will also be tested for its bearing capacity before the constructi­on work begins for this project,” said Sanjay Khandare, Additional Metropolit­an Commission­er, MMRDA.

A design based on the results of the geological survey

would be prepared by the team of contractor­s. “This design would be incorporat­ed during the constructi­on work of MTHL,” said an MMRDA official.

The entire project work has been divided into three phases and separate contractor­s have been assigned for each phase. In the first phase, the bridge will be constructe­d upto 10.38 kms from Sewri and in the 2nd phase, it would extend up to 18.18kms. In the 3rd phase, it is set expected to extend till village Chirle. The 22-km long MTHL sea link is set to provide easy access to Navi Mumbai, Pune Expressway and also to southern India.