The Free Press Journal

First phase of Coastal Road to have three interchang­es: BMC

- AGENCIES / Mumbai

The first phase of the proposed Coastal Road project will have three interchang­es, the Brihanmumb­ai Municipal Corporatio­n (BMC) said on Thursday.

The first phase of this ambitious project runs between Princess Street and BandraWorl­i Sea Link Road and the three interchang­es will be located at Amar Sons Garden, Haji Ali and Worli Seaface, it said. These interchang­es will have 18 alternativ­e routes and nine entry as well as exit routes to facilitate the motorists, the civic body added.

“The total length of these interchang­es will be 14 kms. They will be constructe­d as per the internatio­nal codes of standards and using state-ofthe-art tools,” the BMC said.

The speed limit for vehicles on these interchang­es has been fixed at 40 kmph, it said adding that crash attenuator­s will be installed at important points along these interchang­es to minimise the impact of collision in case of possible accident.

According to a civic official, work on the first phase is expected to start by the next month, when work orders will be issued. The entire project may take almost four years to complete.

“Work on the 10-km stretch from Princess Street Flyover to south end of Bandra Worli Sea Link is likely to start by the end of the year," official said, adding that the first phase will comprise an under-sea tunnel starting from Princess Street flyover to Priyadarsh­ini Circle.

Infrastruc­ture major Larsen and Toubro (L&T) has been awarded the contract to construct a part of the project from Princess Street Flyover to Baroda Palace, including an undergroun­d tunnel passing below Girgaum Chowpatty, Malabar Hills and Priyadarsh­ini Park. The total length of the Coastal Road project is 29.2 kms. The eight-lane road project will start from Princess Street Flyover in Marine Lines and run up to Kandivli.

The standing committee of the BMC had given its nod for the constructi­on of the Rs 12,000-crore project last month.

The speed limit for vehicles on these interchang­es has been fixed at 40 kmph, it said adding that crash attenuator­s will be installed at important points along these interchang­es to minimise the impact of collision in case of possible accident

 ??  ??
 ??  ??

Newspapers in English