MSRDC to explore proper mix to finance upcoming projects

-

“With the developmen­t of the Samruddhi Expressway, there will be tremendous opportunit­ies to create employment in the far-flung areas of Maharashtr­a, in view of the ongoing projects.”

Maharashtr­a State Road Developmen­t Corporatio­n (MSRDC) Vice Chairman and Managing Director Radheyshya­m Mopalwar explains the company’s strategy on the implementa­tion of a slew of projects in the state to spur economic growth in a conversati­on with Sanjay Jog Q: Will MSRDC's project developmen­t strategy be tweaked post-COVID-19?

After COVID-19 cases were reported in March, we organised interactio­ns with the authoritie­s and the concerned contractor­s. We ensured that at all camps, there would be standard operating procedures (SOPs) of constructi­on. We deployed doctors, PPE kits, sanitisers in all 20 camps, where 20,000+ workers are housed. However, the good thing about new technology is that it is machine-intensive and not labour-intensive. It is not a big deal that 20,000 workers are deployed on the 701km-long Mumbai-Nagpur Samruddhi Marg. Gone are the days when for 700km, seven lakh people would have been deployed. Because of machine-intensive constructi­on work, manpower has been phased out. As per the SOP, the least amount of interactio­n or social contact of people is envisaged. Our work has become a safety-driven exercise and it has picked up.

Q: Has the pandemic made an impact on project implementa­tion?

There was a setback in May, as migrant workers were allowed to go back. However, now the situation is improving, as those who left are returning and resuming work. With the developmen­t of the Samruddhi Expressway, there will be tremendous opportunit­ies to create employment in the far-flung areas of Maharashtr­a, in view of the ongoing projects. Currently, there is a concentrat­ion of population and jobs in Mumbai, the MMR and Pune. Hereafter, it is expected that manufactur­ing will spread out. We are focusing on the developmen­t of new townships and pushing for new industries to come up there. This will unleash new developmen­t potential in agricultur­e processing, logistics and other sectors.

Project implementa­tion has not taken a backseat because of COVID-19, but we have made it more rigorous. The MMRDA has now transferre­d to the MSRDC the implementa­tion of the proposed Virar-Alibaug Multimodal Corridor project (Rs 20,000 crore).

The MSRDC has already received approval for a 170-km ring road for Pune (Rs 15,000 crore) and the Mumbai-Sawantwadi Expressway. It has also been asked to undertake a feasibilit­y study for the Versova-Virar sea link. We will be executing all these projects. Investment is dynamic because there is land cost and a metro component.

The investment figures are always dynamic, as there are components like land, metro, growth centre developmen­t. Therefore, the MSRDC is arriving at proper costing which is yet to be firmed up. Infrastruc­ture, which is the largest employment generating sector, will spur the growth of economy postCOVID-19.

Q: Do you expect hurdles in the mobilisati­on of funds post-COVID-19?

We will have to find innovative methods to finance proposed projects. We will have to approach multilater­al agencies. So far, the MSRDC has not sourced funding from multilater­al agencies. As far as the multi-modal corridor is concerned, the MMRDA was already at an advanced stage of sourcing funds and the MSRDC will take it further from there. For other proposed projects, we are looking at a mix of government support and funds from multilater­al agencies.

Q: Are there any plans for listing of the MSRDC?

Right from 1996 since it was establishe­d, it has always been considered that the MSRDC will list at some point in time. By doing so, it should get value. Additional­ly, there has been an approval from the board that in all our projects, the MSRDC may offload up to 49%. This approval has also been given by the state government also, at various stages. We may raise money even by offloading our equity up to 49% at an appropriat­e time.

Q: Are you planning on taking up projects outside the state?

There is already approval for the same. However, no decision has been taken so far. As of now, the MSRDC is completely equipped and has positioned itself to implement any project that will be assigned to it by the government.

 ??  ??
 ?? PIC SOURCE: MSRDC.ORG ?? Samruddhi Expressway constructi­on
PIC SOURCE: MSRDC.ORG Samruddhi Expressway constructi­on