Only 39% desilting work done till date
BMC has deployed another contractor to meet May 31 deadline
Even after receiving the BMC's notice for underperforming, the contractor carrying out desilting work in the island city has completed only 39 per cent of the work till Sunday. So to complete the desilting work before the deadline of May 31, the BMC has simultaneously appointed another contractor.
The BMC administration had set a deadline of May 15 to complete 50 percent desilting work. In a bid to bring transparency in desilting works, the BMC recently launched a live dashboard wherein the citizens can access the status of every nullah being desilted in the city. According to data available from dashboard, only 39 percent of desilting work has been completed by the contractor appointed in the island city for desilting of major nullahs.
The major nullahs in the city are in three civic wards – G South (Worli, Lower Parel), G North (Dharavi, Dadar) and F North (Sion, Matunga). The BMC on May 9 issued a notice for underperforming to the contractor concerned. The notice stated that this is a very serious lapse and negligence. However, even after warning from the BMC no improvement in desilting work seen in the last four days in the city.
The Indian Meteorological Department has predicted early monsoon this year. The desilting work
completed in eastern suburbs is 66 per cent while in western suburbs is 60 per cent.
Ulhas Mahale, deputy municipal commissioner (infrastructure) said, "The present contractor will complete 50 percent work and another contractor is expected to complete the remaining 25 per cent work before May 31. With two contractors working together we will achieve the target."
Meanwhile, the contractor concerned has been asked to submit an explanation within seven days as to why actions such as termination of contract, carrying