New drinking water scheme for added wards in Tiruchi faces fresh hurdles

Pebbles have been found in large numbers on the Cauvery riverbed near Melur where the radial arm, a part of the collector well, is being erected

- C. Jaisankar

The work on the new drinking water project for the ve added wards of Tiruchi Corporatio­n in Kattur and Tiruverumb­ur is facing fresh hurdles due to the pebbles found in large numbers on the riverbed of the Cauvery near Melur where the radial arm, a part of the collector well, is being erected.

The project, which is to be implemente­d at an estimated cost of ₹63.70 crore, is aimed at supplying 135 litres of drinking water per head to residents of 61, 62, 63, 64 and 65 wards in Tiruverumb­ur, Kattur and adjoining areas. In order to expedite the project, Tiruchi Corporatio­n divided it into three components such as constructi­on of head works, constructi­on of reservoirs (overhead tanks) and laying of mains and distributi­on

A view of the pipeline bridge of Thiruverum­bur Mega Water Supply Scheme in Tiruchi.

lines.

The civic body chose a spot at the north end of the Cauvery near Melur to construct a pump house for the drinking water project and began work on two phases, except for the head work phase in 2017. Although constructi­on of reservoirs and laying of mains and distributi­on

were completed more than four years ago, the civic body is yet to complete the head works.

Right from the start of the head work about eight years ago, it has been facing hurdles on various fronts. The work initially got delayed due to opposition of the Melur farmers to draw water from the

Cauvery. It ran into further delay in getting the nod of the Public Works Department and then the Water Resources Department. Even after getting all clearances, the civic body could not make any progress on the constructi­on of head work due to Žow of water in the Cauvery for many months and opening of Mettur dam for irrigation in May 2022 and June 2023.

The closure of the Mettur dam in October 2023, well ahead of schedule, paved the way for starting the head work in full scale. While the civic body has almost completed the head work and a pipe carrying bridge across the Cauvery at Kambarampe­ttai, the erection of a radial arm at the collector’s well, is still on. It was expected that it would be completed by now. However, the largescale deposit of pebbles at the site is said to be posing a great challenge to the engineers and skilled workers. They have to make progress only inch by inch as it requires patience.

“We did not expect pebbles at the collector well site. It requires a team of dedicated and highly skilled work force, who are familiar in radial arm work, to clear the pebbles as it is highly technical. We have no other option but to carry it out in a phased manner. If we show urgency, the system will run into trouble frequently,” says a senior o˜cial involved in the work.

He said there was a dearth of skilled work force specialise­d in those types of work in the State. Only two to three groups were available and frantic ešorts were in place to involve more specialise­d workers in the job. It might take three more months to complete the erection of the radial arm.

The residents of the areas, which were added to Tiruchi Corporatio­n, get just 40 litres of water per day at present. The Tamil Nadu Water and Drainage Board continues to supply water as before the merger of the areas with Tiruchi Corporatio­n. Once completed, the Corporatio­n will take over the responsibi­lity of supplying water to residents from TWAD.