The Indian Express (Delhi Edition)

Bigger network, driverless trains to improve commute

- SWETA DUTTA

METRO

THE DELHI Metro’s massive Phase III project is set for completion and opening in 2017, expanding the Metro network to 315 km, with 227 stations, by the end of the year. The heritage line connecting ITO to Kashmere Gate will be the first to be inaugurate­d by the end of January. The following months will see the opening of two key corridors — Majlis Park to Shiv Vihar (58.59 km) and Janakpuri West to Botanical Garden (38.23 km).

Two other smaller corridors from Dwarka to Najafgarh and Mundka to Bahadurgar­h are also slated to open by the year-end. After the commission­ing of all corridors of Phase III, Metro ridership — is set to go up to 40 lakh per day from the current average of 28 lakh. Fifteen new interchang­e stations will be added to the network to cut down travel time drasticall­y.

Metro is also set to usher in significan­t changes with Unattended Train Operations, or driverless trains, running at a higher frequency, sleeker looking coaches, platform screen doors and stations with artwork.

“Whether constructi­on or operation of Metro, there has been major change from 1997 to now. If you see the Tunnel Boring Machines at constructi­on sites, they are now very sophistica­ted. The other equipment in constructi­on and monitoring equipment, too, have changed drasticall­y. However, the effect visible to public is the change in operation and maintenanc­e. The main concern of the Metro is now to provide additional capacity by running more frequent trains, which means better signalling and improved control system for safety. Today we are at a stage where we have the latest communicat­ion-based train control system (CBTC), where you can have increased capacity by running trains at 90 seconds and also have a very high level of safety,” said Mangu Singh, Managing Director, DMRC.

“The quantum of work in Phase III is Phase I and II put together, almost 140 km, of which 55 km is undergroun­d. We have not really missed deadlines. Earlier, it took us just 15 days to conduct trials before commission­ing the line, but in Phase III, this takes much longer due to the changes in technology,” Singh added.

Meanwhile, Gurgaon is set to see a slew of road and transport developmen­t projects take off in 2017. One of the major projects among these is the launch of the second phase of the Rapid Metro. Phase 2 will begin at Sikanderpu­r Metro station and will cover the city until sector 55-56.

A Rapid Metro spokespers­on said that the process to begin commercial operations “at the earliest” has started. Work has also started on three new underpasse­s in the city — Signature Tower Chowk, Hero Honda Chowk, and IFFCO Chowk — all three of which are prone to heavy congestion and traffic jams. District authoritie­s also expect to make some progress on the plans for the Pod Taxi service, which will connect Gurgaon to Dhaula Kuan, in 2017.