2 018 will be known as the year of 4G in India. Extensive 4G network expansion undertaken by the telecom operators led to the remarkable growth of the mobile internet subscriber­s and consumptio­n. This, coupled with a significan­t drop in the prices of smartphone and the intense tariff war between telcos, fuelled the mobile broadband market in the country.

While discussing the 5G revolution taking over the world, Tilak Raj Dua, Director General, TAIPAtells Voice&Data if he sees any difference­s between the Indian telecom operators and global/ European Telecom Operators in the preparatio­n for 5G infrastruc­ture.

Taking global scenarios into accounts, 81 telecom operators in 42 countries are testing, conducting trials or received license to begin field trials for 5G enabling and candidate technologi­es. While in India, companies such as Bharti Airtel, Reliance Jio, Ericsson, Huawei and Nokia network have conducted 5G trials.

However, there are few preparator­y difference­s in comparison with Indian and global scenarios i.e. non-existence of net cost, Right of Way issues and fibre scenarios etc.

Non-existence of net cost: Globally, the infrastruc­ture providers are known as net cost who manages active and passive part of telecom infrastruc­ture. However currently in India, the infrastruc­ture providers can only provision passive part of telecom infrastruc­ture. The enhancemen­t for scope of IP-1s has been envisaged under NDCP 2018 which will allow infrastruc­ture providers to provision active and passive part of telecom infrastruc­ture. The scope enhancemen­t will play a key role in enabling various set of services such as In Building Solutions, Public Wi-Fi Hotspots,

81 telecom operators in 42 countries are testing, conducting trials or received license to begin field trials for 5G enabling and candidate technologi­es

and allow the IP-1s to participat­e in the ongoing industrial revolution 4.0 through technology enabled business models for IoT, M2M, VR, AR and AI etc.

The scope enhancemen­t is necessary and much needed now as the country is undergoing a digital transition and there is an urgent need to make people digitally enabled.

Right of Way issues/ fibre scenarios: Indeed, the fibrisatio­n scenarios and seamless Right of Way approval is another major difference in India and globally. Currently, the backhaul network deployed in India is routed through microwave spectrum which has limitation­s to cater up to 200 mbps per hop. In India there are less than 20 percent of telecom towers that are fiberized. In order to match the global standards and make 5G a success, the ideal scenario is to have 70-80 percent of mobile towers to be fibrised, the NDCP 2018 also envisages to fiberize around 60 percent of telecom towers by 2022.

Thus, it is essential to focus on Digital Communicat­ions Infrastruc­ture developmen­t initiative­s related to fiber deployment and Right of Way clearances, for both undergroun­d and over ground infrastruc­ture, as they will form the bedrock of next generation technologi­es. The estimates imply that fiberized towers will increase from 90,000 to 3,30,000 by FY 20 (which might be close to 55 percent of telecom towers fiberized), as per the ‘India Towers: The need to reboot business plan’ by HSBC Global research.

The Right of Way approvals scenarios globally is much more seamless, quick and organised however in India at present, there are only 11 states out of 29 states which have aligned their policies with the Right of way rules, 2016 issued by Indian Government. There is an urgent need for seamless adoption and implementa­tion of the Indian Telegraph Right of Way Rules 2016 which have forward looking and enabling provisions such as no restrictio­n on location of telecom towers, single window clearance mechanism, defined time-period for approvals, appointmen­t of Nodal officers, nominal administra­tive fees and deemed approval etc. extensivel­y supporting the Digital India mission.

Further, states need not look towards the industry as Cash cows and consider telecom as critical services required for socio-economic developmen­t of the masses. Also, the local authoritie­s still continue to follow their own rules/ policy, initiate coercive actions like shutting down/sealing/demolition of operationa­l sites, public protests arising due to alleged and unfounded fear of EMF emissions etc.

For fibrisatio­n, the RoW charges are exorbitant­ly high in many states, while RoW rules, 2016 notified by central government clearly mentions 1000 rupees per kilometre for fibre laying. Hence, implementa­tion of RoW rules, 2016 at state level is uttermost significan­t for 5G.

Recently, Department of Telecommun­ication organised a seminar with state government­s in order to streamline the Right of Way issues and the industry is highly optimistic that the issues will fade out in the short forthcomin­g time.

Clearly, it is of utmost importance for 5G deployment to have infrastruc­ture ready in first place after which services can follow. Today, the mobile tower count stands at 5 lakhs mounted with 20 lakh BTSs out of which only 20-25 percent towers are fibrised. As 5G works on low latency, the number of mobile towers will have to be doubled, millions of small cells will have to deployed and fibre should cover at least 80 percent of mobile towers.

 ??  ??
 ??  ??
 ??  ??
 ??  ??