Belfast Telegraph

Lights in NI could go out if interconne­ctor is blocked, court told

- BY ALAN ERWIN

HALTING a planned new £200m cross-border electricit­y line could see Northern Ireland’s “lights go out” by 2021, the High Court has heard.

Counsel for the Department for Infrastruc­ture stressed the urgency surroundin­g a legal challenge to its decision to approve the north-south interconne­ctor.

Up to 6,000 people who own land or live along the proposed route of the pylons and lines are seeking to have the planning permission judicially reviewed.

In January the department announced it was giving the goahead for the Northern Ireland section of the overhead scheme between Tyrone and Meath.

But a group formed under the name Safe Electricit­y A&T (SEAT) issued proceeding­s in a bid to have the decision quashed.

It claims a developmen­t of such regional significan­ce was wrongly approved by a senior civil servant in the absence of a minister.

In a separate case last month the High Court held that a permanent secretary did not have power to give the green light for a £240m waste incinerato­r at Mallusk on the outskirts of north Belfast.

That ruling is being appealed in an attempt to clarify the authority of civil servants without a functionin­g Executive.

However,basedonthe­current legal interpreta­tion, the department’s lawyers accepted SEAT has establishe­d an arguable case atthisstag­eonthecons­titutional point.

It was contended, however, that a second ground of challenge about the potential impact to wildlife should be dismissed.

Barrister Charles Banner, for the department, described the interconne­ctor scheme as having “profound urgency and importance”. He told the court that work is on hold due to the legal challenge. “The lights could go out in 2021 if this project doesn’t proceed,” Mr Banner claimed.

The overall initiative to join electricit­y grids in the two jurisdicti­ons has also been approved in the Republic of Ireland.

It will involve 85 miles of overhead cables and lead to new pylons being built.

Business chiefs have backed the joint scheme between the System Operator for Northern Ireland (SONI) and EirGrid in Ireland to reduce costs and ensure electricit­y supplies.

But residents in border areas who objected to the interconne­ctor instead wanted undergroun­d cables for health and environmen­t reasons — an option dismissed as not feasible.

SEAT’s challenge is centred on approval for more than 100 towers and high-voltage lines.

It also claims the scheme lacks the scientific certainty required under a habitats directive that no harm will be caused to wildlife.

The hearing on whether to grant leave to seek a judicial review was adjourned for amendments to the legal papers.

❝ The cross-border electricit­y line scheme has profound urgency and importance