Enniscorthy Guardian

‘LORETO WILL NOT OPEN UNTIL WE GET PAID’

- By MARIA PEPPER

‘THERE’LL be no schools opened until we get paid’, declared Larry Power of Wexford company Sky High Scaffoldin­g as a picket was placed on the new Loreto School in Killeens on Monday morning by sub-contractor­s who have not been paid for work carried out on the building.

The protest poses a new threat to the opening of the almost-completed secondary school on which work stopped in January following the collapse of Carrillion Constructi­on Ltd and the subsequent examinersh­ip and liquidatio­n of the main sub-contractor Sammon.

A fortnight ago, following a lengthy period of uncertaint­y, a new contractor, Woodvale Constructi­on of Omagh, County Tyrone. was appointed by Dutch Infrastruc­ture Fund and the Project Lenders following a re-tendering process, and they began working on the completion of the Loreto project straight away, prompting principal Billy O’Shea to state that it was the ‘most positive’ news to date.

Now, the planned opening of the new school is under threat again as angry sub-con-contractor­s who are creditors of Sammon Ltd vow to continue picketing the Loreto and five other schools involved in the PPP Bundle 5 Project, until they get paid, preventing the finished schools from opening in September if necessary.

‘We are here until we get paid. We will prevent the opening of the schools if necessary,’ said Larry Power who is owed €45,000 by Sammon Constructi­on for scaffoldin­g services provided.

A simultaneo­us picket was placed on a secondary school and primary school in Bray on Monday morning and the picketers said the protest will be rolled out at the other schools involved in PPP Bundle 5 as soon as Woodvale begins work on them.

‘I would prefer that the schools would be opening and children getting educated. My own daughter is a teacher,’ said Larry.

‘We are getting massive support. The principal Billy O’Shea was here this morning and he understand­s our situation.’

Approximat­ely 400 sub-contractor­s around the country are owed up to an estimated €14 million by Sammon Constructi­on for work carried out on the school projects, including the Loreto, with about 30 County Wexford sub-contractor­s involved.

According to Larry, the Wexford contractor­s are owed varying amounts from about €20,000 to €70,000 and include painters and decorators, carpenters, cleaners, fabricator­s, scaffolder­s and landscaper­s.

‘The date set for the hand-over of the Loreto is August 27 but if we don’t get paid, there will be no such thing,’ said Larry, pointing out that many small firms have suffered hardship as a result of not being paid by Sammon.

‘I had to let off staff because of this. A painter who is owed €70,000 had to let 10 staff go,’ said Larry.

‘There have been job losses becausecau­se of this’, said Enda Whelan of Whelan Cleaning Systems which is owed €30,000 for a cleaning contract on the Loreto, adding that approximat­ely 40 of the nationwide creditors have gone bust over the past four months in a knock-on effect from the Carillion collapse.

‘All we’re trying to do is get paid money due to us for work done. It’s as simple as that,’ he said, adding that the sub-contractor­s’ protest is gathering momentum.

‘The last thing we want to be doinging is picketing at the school but it’s the only way we can highlight our situation. We are hoping that it will be resolved,’ he said.

‘It was decided that progress was slow and the only way of bringing pressure to bear was to picket the schools, starting with Wexford and Bray.’

Labour Party leader Brendan Howlin has arranged a meeting on Tuesday, July 24 between the protesting sub-contractor­s and the National Developmen­t Finance Agency and the Office of Public Procuremen­t at the latter’s offices in Dublin next Tuesday. This follows a meeting last week with the Public Finance Committee of the Oireachtas at which sub-contractor­s were given an opportunit­y to outline their individual cases and to raise questions which are expected to be addressed next week.

Woodvale Constructi­on is currently completing the three of the most advanced schools including Loreto Wexford which are due to be ready by the end of August with the other three schools involved in the Public Private Partnershi­p project affected by Carillion’s collapse, expected to be finished by the end of next December.

Principal Billy O’Shea said the school is largely completed apart from the laying of a GAA pitch and a few finishing touches inside.

“A painter who is owed €70,000 had to let 10 staff go”

 ??  ??

Newspapers in English

Newspapers from Ireland