Irish Independent

More wind and solar farms needed now to hit climate targets, ministers warned

Data centres also identified as issue by advisory group

- CAROLINE O’DOHERTY ENVIRONMEN­T CORRESPOND­ENT

The Government’s climate advisers have warned more wind and solar farms must be built urgently to meet the need for clean electricit­y.

In a critical review published today, the Climate Change Advisory Council (CC AC) says no new planning permission­s for renewable projects were granted for 12 months up to last September.

The wind farm given the go-ahead then is now being appealed against and three others approved since are under judicial review. While electricit­y generation from renewable sources increased slightly last year, the CCAC says, it remains “significan­tly below the annual increase needed to meet growing demand and simultaneo­usly satisfy 2030 targets for emission reductions”.

“Delays and appeals in the planning process for onshore wind projects in particular are significan­tly hindering progress,” it says.

The CCAC is calling for new regulation­s to fast-track planning permission for onshore turbines and solar arrays.

An EU directive allowing for the creation of “renewables accelerati­on areas” is due to be put into Irish law by July 1 and the CCAC says that must happen on schedule.

It would allow for central government to designate areas for renewable electricit­y projects of “overriding public interest”, sidesteppi­ng local authoritie­s which have largely failed to zone for them.

Environmen­tal assessment­s would be carried out in advance, meaning any project proposed for a designated area would not have to repeat the process.

The electricit­y sector is the third largest producer of greenhouse gas emissions in Ireland, after agricultur­e and transport.

Its emissions come chiefly from fossil fuel-fired generating stations, one waste-to-energy facility, one natural gas production platform and one natural gas refinery.

Up to the end of 2023 it also came from the peat-powered electricit­y plant at Edenderry, which has since switched to biomass, but the CCAC said a recent announceme­nt that it was to be connected to the gas network was “problemati­c”.

The continued burning of coal, the most carbon-intensive fuel, at the Moneypoint plant was also a problem and must end “at the earliest opportunit­y”.

The CCAC also has a strong warning about data centres, which used 18pc of all electricit­y in Ireland last year.

“For context, electricit­y demand from data centres accounts for 1.5pc of global electricit­y use and an estimated 1.8 – 2.6pc of the total EU electricit­y demand,” it said.

“The expansion in renewable electricit­y generation capacity is significan­tly outpaced by the growth in electricit­y demand, largely driven by data centres.

“It will be increasing­ly difficult to remain within the carbon budgets [emissions restrictio­ns] if data centres continue to be connected before the country has the renewable capacity to accommodat­e them.”

Some data centres are seeking gas connection­s in order to generate their own electricit­y on site but while this would ease the demand for electricit­y from the national grid, it increases emissions.

The CCAC calls for Gas Networks Ireland (GNI) to be directed not to connect up any more data centres but it acknowledg­es that the law setting up GNI requires it to provide connection­s on request.

“The Government should immediatel­y align the legal mandate for all public bodies to have regard to the Climate Action and Low Carbon Developmen­t (Amendment) Act 2021, particular­ly those operating in the energy sphere, such as the CRU, EirGrid, ESB Networks and Gas Networks Ireland,” it said.

CCAC chairwoman Marie Donnelly said the review was a stark reminder of the critical actions needed to ensure that the electricit­y sector reduced its emissions while catering for a growing demand.

“The Government must now move urgently to finalise all elements of planning reform that will help accelerate renewable delivery,” she said.

“Government must show leadership and take the actions required to ensure that Ireland can quickly capitalise on resources that we know are available but cannot come online due to system blockages. We know the potential – we now must have it realised.”

Other recommenda­tions in the review focus on limiting peak-time demand for electricit­y by encouragin­g households and businesses to spread out their power usage where possible.

Peak-time surges in demand mean all available generators are brought into full production, including Moneypoint and the oil-fired plants which are the most polluting.

While 1.6 million households have smart meters, the CCAC says just 330,000 are making use of them to switch to smart tariffs that incentivis­e off-peak use.

The take-up rate must be increased, it says.

Similarly, large energy-using businesses must be better incentivis­ed to shift power usage to off-peak periods.

The CCAC also calls for urgent attention to get more “grid” – cables, pylons and substation­s – installed to ensure all wind energy generated can be captured and dispersed. Wind farms often have to power down because the local grid is overloaded and cannot take all the electricit­y they produce.

According to the CCAC, half of all grid projects undertaken by EirGrid are at least a year behind schedule.

“Government must show leadership and take the actions required to ensure that Ireland can quickly capitalise on resources that we know are available but cannot come online due to system blockages”

Newspapers in English

Newspapers from Ireland