New Ross Standard

WORK UNDER WAY ON MAIN SPAN OF BARROW BRIDGE

- BY DAVID LOOBY

WORK has begun on the main span of the Barrow Bridge starting with travellers being erected to facilitate the constructi­on works.

A BAM Iridium spokespers­on said: ‘ The River Barrow Bridge is progressin­g with three sections of the deck poured on the west side of the River Barrow and the support falsework being erected on the east side of the river.’

The first pour was expected towards the end of March. The travellers, which are bespoke designed falsework, are being erected at Pier 4 and on the west side of the river and will support the falsework for pouring the deck.

‘ They will “creep” along pouring the deck itself from previously poured sections.’

Earthworks are moving towards the final stages in many areas of the project, with drainage being installed, stabilisat­ion started and cement bound granular mixture (CBGM) about to start in earnest. Work is continuing on the deck constructi­on west of the river, while pier constructi­on is nearing completion. Formwork erection for the deck east of river is being carried out.

Most of the local roads that cross the route have had the structures installed with traffic now passing through in the next few weeks. ‘We will be putting final surfaces on the roads, installing safety barriers and signage,’ the spokespers­on said. The N25 at Glenmore is in Phase 3 of traffic management. ‘ This will allow us to finish the underbridg­e and complete the roundabout – the next Traffic Management switch is planned for the end of April.’

Structures are at finishing stages at most of the locations, the structure on L4013 (Lacken South) is due for completion in June. The structures at Ballyverne­en are on course for completion in the third quarter of 2018. Traffic management is in place in numerous locations from N25 at Glenmore all the way through to Corcoran’s Cross (N30). Two bridges in Ballyverne­en and finishing works to bridges across the 14km site are under way. Accommodat­ion works for landowners. earthworks: drainage, cut and fill operations, stabilisat­ion and topsoiling works are all being carried out.

Upcoming works include concluding work on Lacken South and progressin­g the Ballyverne­en underbridg­e. Accommodat­ion works include surfacing, drainage and fencing works. Drainage stabilisat­ion and surfacing. Road Diversions will include Glenmore Phase 4 and local roads. Signage and safety barrier installati­on will take place on the routes.

 ??  ??
 ??  ??

Newspapers in English

Newspapers from Ireland